ENTE REGIONE MARCHE
Amount
Award date
Bids
Published
Estimated tender value
Applicable legal ceiling
National maximum for this procedure type under D.Lgs 36/2023 — verify on official sources.
Award vs estimate
Sector
Loading actions…
Publication / start of procedure
16 Jan 2013
Step completedTime to submit bids
4 Apr 2013
78 days between opening and deadline
Step completedAward
24 Jun 2016
Step completedContract signed
29 Jun 2016
Step completedContract variation
4 Aug 2026
Step completedWork suspension
13 Mar 2020
Step completedWorks progress (SAL)
6 Aug 2026
Loading…
These are automated checks on public data. They help you decide what to look into — they are not criminal findings.
This contract triggered 9 pattern(s) worth a closer look:
Variation on record · Multiple variations
| Supplier | Region | Amount | Award date | Status |
|---|---|---|---|---|
| CARRON CAV. ANGELO S.P.A. CON UNICO SOCIO | — | €50,148,002 | 24 Jun 2016 | AGGIUDICATA |
| LANDI S.P.A. | — | €50,148,002 | 24 Jun 2016 | AGGIUDICATA |
| GIANNI BENVENUTO - S.P.A. | — | €50,148,002 | 24 Jun 2016 | AGGIUDICATA |
Variations
ESIGENZE DERIVANTI DA SOPRAVVENUTE DISPOSIZIONI LEGISLATIVE E REGOLAMENTARI, ESIGENZE DERIVANTI DA CAUSE IMPREVISTE E IMPREVEDIBILI E ESIGENZE FINALIZZATE AL MIGLIORAMENTO DELL''OPERA E ALLA SUA FUNZIONALITÀ MOTIVATE DA OBIETTIVE ESIGENZE DERIVANTI DA CIRCOSTANZE SOPRAVVENUTE E IMPREVEDIBILI AL MOMENTO DELLA STIPULA DEL CONTRATTO.
Approved on 4 Aug 2026 · 99
ESIGENZE DERIVANTI DA SOPRAVVENUTE DISPOSIZIONI LEGISLATIVE E REGOLAMENTARI, ESIGENZE DERIVANTI DA CAUSE IMPREVISTE E IMPREVEDIBILI E ESIGENZE FINALIZZATE AL MIGLIORAMENTO DELL''OPERA E ALLA SUA FUNZIONALITÀ MOTIVATE DA OBIETTIVE ESIGENZE DERIVANTI DA CIRCOSTANZE SOPRAVVENUTE E IMPREVEDIBILI AL MOMENTO DELLA STIPULA DEL CONTRATTO.
Approved on 23 Dec 2025 · 99
ESIGENZE DERIVANTI DA SOPRAVVENUTE DISPOSIZIONI LEGISLATIVE E REGOLAMENTARI, ESIGENZE DERIVANTI DA CAUSE IMPREVISTE E IMPREVEDIBILI E ESIGENZE FINALIZZATE AL MIGLIORAMENTO DELL''OPERA E ALLA SUA FUNZIONALITÀ MOTIVATE DA OBIETTIVE ESIGENZE DERIVANTI DA CIRCOSTANZE SOPRAVVENUTE E IMPREVEDIBILI AL MOMENTO DELLA STIPULA DEL CONTRATTO .
Approved on 20 Dec 2024 · 99
ART.132 C.3 II CV D.LGS.163/2006
Approved on 22 Dec 2023 · 6
ART.132 C.1 LETT. B) D.LGS.163/2006
Approved on 15 Dec 2022 · 2
ART.132 C.3 II CV D.LGS.163/2006
Approved on 7 Jul 2020 · 6
ART.132 C.1 LETT. A) D.LGS.163/2006
Approved on 11 Dec 2018 · 1
ART.132 C.3 II CV D.LGS.163/2006
Approved on 10 Nov 2017 · 6
Suspensions
CAUSE DI FORZA MAGGIORE
From 13 Mar 2020 · resumed on 27 May 2020
CAUSE DI FORZA MAGGIORE
From 13 Mar 2020 · resumed on 27 May 2020
CAUSE DI FORZA MAGGIORE
From 13 Mar 2020 · resumed on 27 May 2020
CAUSE DI FORZA MAGGIORE
From 13 Mar 2020 · resumed on 27 May 2020
CAUSE DI FORZA MAGGIORE
From 13 Mar 2020 · resumed on 27 May 2020
CAUSE DI FORZA MAGGIORE
From 13 Mar 2020 · resumed on 27 May 2020
AVVERSE CONDIZIONI CLIMATICHE
From 26 Feb 2018 · resumed on 8 Mar 2018
AVVERSE CONDIZIONI CLIMATICHE
From 26 Feb 2018 · resumed on 8 Mar 2018
AVVERSE CONDIZIONI CLIMATICHE
From 26 Feb 2018 · resumed on 8 Mar 2018
AVVERSE CONDIZIONI CLIMATICHE
From 26 Feb 2018 · resumed on 8 Mar 2018
AVVERSE CONDIZIONI CLIMATICHE
From 26 Feb 2018 · resumed on 8 Mar 2018
AVVERSE CONDIZIONI CLIMATICHE
From 26 Feb 2018 · resumed on 8 Mar 2018
INTERFERENZE DI NATURA AMMINISTRATIVA
From 11 Jul 2016 · resumed on 6 Dec 2017
INTERFERENZE DI NATURA AMMINISTRATIVA
From 11 Jul 2016 · resumed on 6 Dec 2017
INTERFERENZE DI NATURA AMMINISTRATIVA
From 11 Jul 2016 · resumed on 6 Dec 2017
INTERFERENZE DI NATURA AMMINISTRATIVA
From 11 Jul 2016 · resumed on 6 Dec 2017
INTERFERENZE DI NATURA AMMINISTRATIVA
From 11 Jul 2016 · resumed on 6 Dec 2017
INTERFERENZE DI NATURA AMMINISTRATIVA
From 11 Jul 2016 · resumed on 6 Dec 2017
STATO DI AVANZAMENTO N.1
Issued 13 Jul 2018 · €1,056,296 · payment certified 20 Jul 2018 · delay flagged
STATO DI AVANZAMENTO N.2
Issued 16 Nov 2018 · €2,650,791 · payment certified 12 Dec 2018 · delay flagged
STATO DI AVANZAMENTO N.3
Issued 15 Nov 2019 · €3,685,521 · payment certified 13 Dec 2019 · delay flagged
STATO AVANZAMENTO LAVORI N.4 AL 07/08/2020
Issued 7 Aug 2020 · €7,034,536 · payment certified 21 Sept 2020 · delay flagged
SAL N.5 E ANTICIPO DEL 30% DELL'IMPORTO CONTRATTUALE,\\R\\NAI SENSI DELL'ART.207 DEL D.L. N. 34/2020, CONVERTITO, CON MODIFICAZIONI, DALLA LEGGE 17 LUGLIO 2020, N.77
Issued 25 Nov 2020 · €11,700,211 · payment certified 14 Dec 2020 · delay flagged
STATO AVANZAMENTO LAVORI N.6 AL 31/01/2021
Issued 4 Mar 2021 · €14,827,788 · payment certified 8 Mar 2021 · delay flagged
STATO AVANZAMENTO LAVORI N.7 AL 03/04/2021
Issued 3 Apr 2021 · €17,999,742 · payment certified 25 May 2021 · delay flagged
STATO AVANZAMENTO LAVORI N.8 AL 31/05/2021
Issued 31 May 2021 · €22,286,141 · payment certified 4 Aug 2021 · delay flagged
STATO AVANZAMENTO LAVORI N.9 AL 06/08/2021
Issued 6 Aug 2021 · €27,139,327 · payment certified 6 Oct 2021 · delay flagged
STATO AVANZAMENTO LAVORI N.10 AL 31/10/2021
Issued 9 Dec 2021 · €32,458,971 · payment certified 9 Dec 2021 · delay flagged
STATO AVANZAMENTO LAVORI N.11 AL 30/12/2021
Issued 28 Feb 2022 · €36,579,569 · payment certified 28 Feb 2022 · delay flagged
STATO AVANZAMENTO LAVORI N.12 AL 28/02/2022
Issued 29 Apr 2022 · €40,042,613 · payment certified 29 Apr 2022 · delay flagged
STATO AVANZAMENTO LAVORI N.13 AL 30/04/2022
Issued 30 Jun 2022 · €44,168,251 · payment certified 30 Jun 2022 · delay flagged
STATO AVANZAMENTO LAVORI N.14 AL 31/07/2022
Issued 29 Aug 2022 · €48,395,635 · payment certified 30 Aug 2022 · delay flagged
STATO AVANZAMENTO LAVORI N.15 AL 31/10/2022
Issued 30 Nov 2022 · €53,079,821 · payment certified 30 Nov 2022 · delay flagged
STATO AVANZAMENTO LAVORI N.16 AL 31/12/2022
Issued 27 Jan 2023 · €57,052,413 · payment certified 1 Feb 2023 · delay flagged
STATO AVANZAMENTO LAVORI N.17 AL 31/03/2023
Issued 6 Apr 2023 · €61,282,911 · payment certified 12 Apr 2023 · delay flagged
STATO AVANZAMENTO LAVORI N.18 AL 30/06/2023
Issued 10 Jul 2023 · €65,354,277 · payment certified 11 Jul 2023 · delay flagged
STATO AVANZAMENTO LAVORI N.19 AL 30/09/2023
Issued 25 Oct 2023 · €68,034,933 · payment certified 26 Oct 2023 · delay flagged
STATO AVANZAMENTO LAVORI N.20 AL 31/12/2023
Issued 26 Jan 2024 · €70,608,000 · payment certified 26 Jan 2024 · delay flagged
STATO AVANZAMENTO LAVORI N.21 AL 31/03/2024
Issued 23 Apr 2024 · €73,165,665 · payment certified 24 Apr 2024 · delay flagged
STATO AVANZAMENTO LAVORI N.22 AL 30/06/2024
Issued 22 Jul 2024 · €75,683,282 · payment certified 23 Jul 2024 · delay flagged
STATO AVANZAMENTO LAVORI N.23 AL 30/09/2024
Issued 18 Oct 2024 · €78,188,452 · payment certified 21 Oct 2024 · delay flagged
STATO AVANZAMENTO LAVORI N.24 AL 31/12/2024
Issued 29 Jan 2025 · €84,262,661 · payment certified 30 Jan 2025 · delay flagged
STATO AVANZAMENTO LAVORI N. 25 AL 31/03/2025
Issued 29 Apr 2025 · €87,319,931 · payment certified 30 Apr 2025 · delay flagged
STATO AVANZAMENTO LAVORI N. 26 AL 31/05/2025
Issued 17 Jul 2025 · €90,873,466 · payment certified 18 Jul 2025 · delay flagged
STATO AVANZAMENTO LAVORI N. 27 AL 30/09/2025
Issued 30 Oct 2025 · €95,226,003 · payment certified 3 Nov 2025 · delay flagged
STATO AVANZAMENTO LAVORI N. 28 AL 31/12/2025
Issued 20 Feb 2026 · €102,524,139 · payment certified 23 Feb 2026 · delay flagged
STATO AVANZAMENTO LAVORI N. 29 AL 31/03/2026
Issued 8 May 2026 · €107,721,004 · payment certified 11 May 2026 · delay flagged
STATO AVANZAMENTO LAVORI N. 30 AL 04/08/2026
Issued 6 Aug 2026 · €113,381,734 · payment certified 6 Aug 2026 · delay flagged
Loading comparison…
In sector Construction works in Marche, 8.8% of comparable tenders drew at least 3 bidders (of 19167 tenders).
8.8% of comparable tenders had ≥3 bidders (n=19167)
Loading…
Loading…
Loading…
ANAC BDNCP — dati tabellari
Verify on ANACIngested: 20 Sept 2026
Release: 20260801-cig_csv.csv
Days to submit bids: 78