PARCO STURA SPONDA DESTRA 1° STRALCIO - COMPLETAMENTO (COD. OPERA 3737 - CUP.C17B10000000004)
COMUNE DI TORINO
Amount
Award date
Bids
Published
Estimated tender value
Applicable legal ceiling
National maximum for this procedure type under D.Lgs 36/2023 — verify on official sources.
Award vs estimate
Sector
Loading actions…
Publication / start of procedure
30 Jan 2012
Step completedTime to submit bids
13 Mar 2012
43 days between opening and deadline
Step completedAward
28 Dec 2015
Step completedContract signed
23 Jul 2013
Step completedContract variation
13 Oct 2014
Step completedWork suspension
9 Mar 2015
Step completedWorks progress (SAL)
19 Apr 2015
Loading…
These are automated checks on public data. They help you decide what to look into — they are not criminal findings.
This contract triggered 6 pattern(s) worth a closer look:
Discount very different from similar tenders · Works delayed (SAL)
- Discount very different from similar tenders What does this mean?
- Works delayed (SAL) What does this mean?
- Long extension What does this mean?
- Final cost well above award
- No closure recorded
- Significant subcontracting
| Supplier | Region | Amount | Award date | Status |
|---|---|---|---|---|
| EDIL EUROPA S.R.L. | — | €527,008 | 28 Dec 2015 | AGGIUDICATA |
| Organisation | Role | Outcome |
|---|---|---|
| EDIL EUROPA S.R.L. 03117750012 | Not reported | Awarded |
Variations
ART 132 C.3 2° PERIODO
Approved on 13 Oct 2014 · 99
Suspensions
AVVERSE CONDIZIONI CLIMATICHE
From 9 Mar 2015 · resumed on 23 Mar 2015
AVVERSE CONDIZIONI CLIMATICHE
From 9 Mar 2015 · resumed on 23 Mar 2015
AVVERSE CONDIZIONI CLIMATICHE
From 9 Mar 2015 · resumed on 23 Mar 2015
AVVERSE CONDIZIONI CLIMATICHE
From 9 Mar 2015 · resumed on 23 Mar 2015
AVVERSE CONDIZIONI CLIMATICHE
From 9 Mar 2015 · resumed on 23 Mar 2015
AVVERSE CONDIZIONI CLIMATICHE
From 9 Mar 2015 · resumed on 23 Mar 2015
AVVERSE CONDIZIONI CLIMATICHE
From 9 Mar 2015 · resumed on 23 Mar 2015
AVVERSE CONDIZIONI CLIMATICHE
From 2 Feb 2015 · resumed on 11 Feb 2015
AVVERSE CONDIZIONI CLIMATICHE
From 2 Feb 2015 · resumed on 11 Feb 2015
AVVERSE CONDIZIONI CLIMATICHE
From 2 Feb 2015 · resumed on 11 Feb 2015
AVVERSE CONDIZIONI CLIMATICHE
From 2 Feb 2015 · resumed on 11 Feb 2015
AVVERSE CONDIZIONI CLIMATICHE
From 2 Feb 2015 · resumed on 11 Feb 2015
AVVERSE CONDIZIONI CLIMATICHE
From 2 Feb 2015 · resumed on 11 Feb 2015
AVVERSE CONDIZIONI CLIMATICHE
From 2 Feb 2015 · resumed on 11 Feb 2015
CAUSE DI FORZA MAGGIORE
From 5 May 2014
CAUSE DI FORZA MAGGIORE
From 5 May 2014
CAUSE DI FORZA MAGGIORE
From 5 May 2014
CAUSE DI FORZA MAGGIORE
From 5 May 2014
CAUSE DI FORZA MAGGIORE
From 5 May 2014
CAUSE DI FORZA MAGGIORE
From 5 May 2014
CAUSE DI FORZA MAGGIORE
From 5 May 2014
AVVERSE CONDIZIONI CLIMATICHE
From 3 Feb 2014 · resumed on 10 Mar 2014
AVVERSE CONDIZIONI CLIMATICHE
From 3 Feb 2014 · resumed on 10 Mar 2014
AVVERSE CONDIZIONI CLIMATICHE
From 3 Feb 2014 · resumed on 10 Mar 2014
AVVERSE CONDIZIONI CLIMATICHE
From 3 Feb 2014 · resumed on 10 Mar 2014
AVVERSE CONDIZIONI CLIMATICHE
From 3 Feb 2014 · resumed on 10 Mar 2014
AVVERSE CONDIZIONI CLIMATICHE
From 3 Feb 2014 · resumed on 10 Mar 2014
AVVERSE CONDIZIONI CLIMATICHE
From 3 Feb 2014 · resumed on 10 Mar 2014
Progress step 1
Issued 23 Jul 2013 · €160,601 · payment certified 8 Aug 2013 · delay flagged
Progress step 2
Issued 31 Jan 2014 · €318,247 · payment certified 12 Feb 2014 · delay flagged
Progress step 3
Issued 4 May 2014 · €516,502 · payment certified 22 May 2014 · delay flagged
Progress step 4
Issued 27 Mar 2015 · €667,393 · payment certified 26 May 2015 · delay flagged
Progress step 5
Issued 19 Apr 2015 · €727,578 · payment certified 21 Jul 2015 · delay flagged
Loading comparison…
In sector Construction works in Piedmont, 8.7% of comparable tenders drew at least 3 bidders (of 31488 tenders).
8.7% of comparable tenders had ≥3 bidders (n=31488)
Loading…
Loading…
Loading…
Source data & verification
ANAC BDNCP — dati tabellari
Verify on ANACIngested: 20 Sept 2026
Release: 20260801-cig_csv.csv
Days to submit bids: 43