Key figures from open ANAC records for this contract.

Amount

€1,673,777

Award date

20 Feb 2025

Bids

1

Published

28 Jan 2025

Estimated tender value

€836,889

Applicable legal ceiling

€150,000

National maximum for this procedure type under D.Lgs 36/2023 — verify on official sources.

Award vs estimate

+100.0%

Sector

Construction worksLAVORI DI COSTRUZIONE DI CONDOTTE PER TELERISCALDAMENTO
How do I verify this tender?

Loading actions…

Timeline
  1. Publication / start of procedure

    28 Jan 2025

    Step completed
  2. Time to submit bids

    17 Feb 2025

    20 days between opening and deadline

    Step completed
  3. Award

    20 Feb 2025

    Step completed
  4. Contract signed

    19 Mar 2025

    Step completed
  5. Works progress (SAL)

    29 Jul 2026

Delivery record

Loading…

In plain language

These are automated checks on public data. They help you decide what to look into — they are not criminal findings.

This contract triggered 5 pattern(s) worth a closer look:

Low competition · Negotiated without call

Contracting authority (buyer)
PRIMIERO ENERGIA CALORE S.P.A.

Trentino-South Tyrol · More tenders in this area

AUSA code: 0000272123

PRIMIERO SAN MARTINO DI CASTROZZA

Authority profile
Awarded to (suppliers)
2 award line(s) on record.
SupplierRegionAmountAward dateStatus
ATZWANGER S.P.A.€836,88920 Feb 2025AGGIUDICATA
ZUGLIANI S.R.L.€836,88920 Feb 2025AGGIUDICATA
Who took part
2 participant(s) recorded on ANAC (not only the winner).
OrganisationRoleOutcome
ATZWANGER S.P.A.

02227070212

MANDATARIAAwarded
ZUGLIANI S.R.L.

01096460223

MANDANTEAwarded
Works progress (SAL)
Progress certificates (stati di avanzamento) from ANAC — amounts and delays as published.
  • AVANZAMENTO N. 1

    Issued 19 Mar 2025 · €142,367 · payment certified 24 Apr 2025 · delay flagged

  • AVANZAMENTO N. 2

    Issued 12 Jun 2025 · €370,937 · payment certified 16 Jun 2025 · delay flagged

  • AVANZAMENTO N. 3

    Issued 7 Nov 2025 · €521,882 · payment certified 7 Nov 2025 · delay flagged

  • AVANZAMENTO N. 4

    Issued 22 Dec 2025 · €679,241 · payment certified 22 Dec 2025 · delay flagged

  • AVANZAMENTO N. 5

    Issued 30 Apr 2026 · €962,400 · payment certified 14 Jun 2026 · delay flagged

  • AVANZAMENTO N. 6

    Issued 17 Jun 2026 · €1,283,095 · payment certified 17 Jun 2026 · delay flagged

  • AVANZAMENTO N. 7

    Issued 29 Jul 2026 · €1,423,196 · payment certified 12 Sept 2026 · delay flagged

Similar tenders in the same area

Loading comparison…

Market peer context
Market context from ANAC open data — not a full DIGIWHIST calibration.

Single bidder — In sector Construction works in Trentino-South Tyrol, 9.9% of comparable tenders drew at least 3 bidders (of 23630 tenders). The score alone does not say whether that is unusual; this context does.

9.9% of comparable tenders had ≥3 bidders (n=23630)

UIF-aligned indicator (experimental)
Open-data risk indicator — for further review. Not a UIF/Bank of Italy endorsement.
Sector comparison

Loading…

Amount vs category

Loading…

Discount vs similar tenders

Loading…

Citizen verifier notes
Share what you verified on official sources — not a verdict
How the score is built
Ruleset 3.3.1 · 20 Sept 2026
Source data & verification

ANAC BDNCP — dati tabellari

Verify on ANAC

Ingested: 27 Jun 2026

Release: cig_csv_2025_01

Days to submit bids: 20

RETE SAN MARTINO E PRIMIERO_AMPLIAMENTO RETE A SEGIUITO DI RICHIESTE NUOVE UTENZE. ANNO 2025-2026 — AppaltiWatch