COMUNE DI CIVATE AFFIDAMENTO DEI LAVORI DI 'INTERVENTO DI RICOSTRUZIONE DEL FABBRICATO E RIQUALIFICAZIONE AREA A VERDE EX MEXICO IN LOC.ISELLA'.
COMUNE DI CIVATE
Amount
Award date
Bids
Published
Estimated tender value
Applicable legal ceiling
National maximum for this procedure type under D.Lgs 36/2023 — verify on official sources.
Award vs estimate
Sector
Loading actions…
Publication / start of procedure
3 Aug 2023
Step completedTime to submit bids
5 Sept 2023
33 days between opening and deadline
Step completedAward
13 Sept 2023
Step completedContract signed
25 May 2024
Step completedContract variation
8 Aug 2025
Step completedWork suspension
26 Sept 2025
Step completedWorks progress (SAL)
28 Jan 2025
Loading…
These are automated checks on public data. They help you decide what to look into — they are not criminal findings.
This contract triggered 4 pattern(s) worth a closer look:
Negotiated without call · Works delayed (SAL)
- Negotiated without call What does this mean?
- Works delayed (SAL) What does this mean?
- No start recorded
- Funding source not reported
| Supplier | Region | Amount | Award date | Status |
|---|---|---|---|---|
| PALADINO COSTRUZIONI S.R.L. | — | €789,199 | 13 Sept 2023 | AGGIUDICATA |
| Organisation | Role | Outcome |
|---|---|---|
| PALADINO COSTRUZIONI S.R.L. 07455410964 | Not reported | Awarded |
Variations
ART. 120, COMMA 1, LETTERA B) DEL D.LGS. 36/2023, SENZA UNA NUOVA PROCEDURA DI AFFIDAMENTO, SE L?EVENTUALE AUMENTO DI PREZZO NON ECCEDE IL 50% DEL VALORE DEL CONTRATTO INIZIALE, COSÌ COME PREVISTO AL COMMA 2 DEL MEDESIMO ARTICOLO
Approved on 8 Aug 2025 · 99
SCAVO DI FONDAZIONE: NELLA ZONA A VALLE IL TERRENO HA PRESENTATO UNA FASCIA ARGILLOSA CON SCARSA PORTATA STRUTTURALE, E SI PROCEDUTO AD INCREMENTARE LO SCAVO FINO AL RAGGIUNGIMENTO DELLA ROCCIA SOTTOSTANTE
Approved on 5 Dec 2024 · 99
Suspensions
CAUSE DI FORZA MAGGIORE
From 26 Sept 2025 · resumed on 1 Oct 2025
CAUSE DI FORZA MAGGIORE
From 26 Sept 2025 · resumed on 1 Oct 2025
REDAZIONE DI VARIANTI IN CORSO DI ESECUZIONE
From 20 Nov 2024 · resumed on 6 Dec 2024
REDAZIONE DI VARIANTI IN CORSO DI ESECUZIONE
From 20 Nov 2024 · resumed on 6 Dec 2024
AVVERSE CONDIZIONI CLIMATICHE
From 30 May 2024 · resumed on 2 Jul 2024
AVVERSE CONDIZIONI CLIMATICHE
From 30 May 2024 · resumed on 2 Jul 2024
AVVERSE CONDIZIONI CLIMATICHE
From 23 Feb 2024 · resumed on 20 Mar 2024
AVVERSE CONDIZIONI CLIMATICHE
From 23 Feb 2024 · resumed on 20 Mar 2024
CAUSE DI FORZA MAGGIORE
From 13 Nov 2023 · resumed on 3 Jan 2024
CAUSE DI FORZA MAGGIORE
From 13 Nov 2023 · resumed on 3 Jan 2024
INTERVENTO DI RICOSTRUZIONE DEL FABBRICATO E RIQUALIFICAZIONE AREA A VERDE (EX MEXICO) IN LOCALITÀ ISELLA. APPROVAZIONE 1° STATO DI AVANZAMENTO LAVORI A TUTTO IL 25.05.2024
Issued 25 May 2024 · €269,683 · delay flagged
INTERVENTO DI RICOSTRUZIONE DEL FABBRICATO E RIQUALIFICAZIONE AREA A VERDE (EX MEXICO) IN LOCALITÀ ISELLA. APPROVAZIONE 2° STATO DI AVANZAMENTO LAVORI A TUTTO IL 30.09.2024
Issued 30 Sept 2024 · €415,981 · delay flagged
INTERVENTO DI RICOSTRUZIONE DEL FABBRICATO E RIQUALIFICAZIONE AREA A VERDE (EX MEXICO) IN LOCALITÀ ISELLA. APPROVAZIONE 3° STATO DI AVANZAMENTO LAVORI A TUTTO IL 20.01.2025
Issued 28 Jan 2025 · €671,545 · delay flagged
Loading comparison…
In sector Construction works in Lombardy, 10.7% of comparable tenders drew at least 3 bidders (of 49549 tenders).
10.7% of comparable tenders had ≥3 bidders (n=49549)
Loading…
Loading…
Loading…
Source data & verification
ANAC BDNCP — dati tabellari
Verify on ANACIngested: 5 Aug 2026
Release: 20260401-cig_csv.csv
Days to submit bids: 33