APPALTO 46/2022 - NUOVA BIBLIOTECA LORENTEGGIO DI VIA E. ODAZIO. CUP B43J18000130004 - INVESTIMENTO PNRR: M5C2-INVESTIMENTO 2.3 - PROGRAMMA INNOVATIVO NAZIONALE PER LA QUALITÀ DELL'ABITARE
COMUNE DI MILANO
Amount
Award date
Bids
Published
Estimated tender value
Applicable legal ceiling
National maximum for this procedure type under D.Lgs 36/2023 — verify on official sources.
Award vs estimate
Sector
Loading actions…
2022 general election · 25 Sept 2022
11 days before the election date on record.
Publication / start of procedure
28 Jul 2022
Step completedTime to submit bids
20 Sept 2022
54 days between opening and deadline
Step completedAward
6 Oct 2022
Step completedContract signed
5 Jun 2023
Step completedContract variation
27 Apr 2026
Step completedWork suspension
23 Dec 2024
Step completedWorks progress (SAL)
31 Mar 2026
Loading…
These are automated checks on public data. They help you decide what to look into — they are not criminal findings.
This contract triggered 7 pattern(s) worth a closer look:
Low competition · Near elections — worth reviewing
- Tender with a single bidder What does this mean?
- Publish or award date near an election date (temporal pattern) What does this mean?
- Discount very different from similar tenders What does this mean?
- Works delayed (SAL) What does this mean?
- Long extension What does this mean?
- No start recorded
- Funding source not reported
| Supplier | Region | Amount | Award date | Status |
|---|---|---|---|---|
| SI.GE.CO COSTRUZIONI S.R.L. | — | €4,164,662 | 6 Oct 2022 | AGGIUDICATA |
| Organisation | Role | Outcome |
|---|---|---|
| SI.GE.CO COSTRUZIONI S.R.L. 05087340633 | Not reported | Awarded |
Variations
ESECUZIONE DI MAGGIORI OPERE AI SENSI DELL''ART. 106 COMMA 1 LETT. C) E COMMA 2 LETT. B) DEL D.LGS. 50/2016
Approved on 27 Apr 2026 · 99
SOPRAVVENUTE ESIGENZE NORMATIVE E REGOLAMENTARI
Approved on 17 Oct 2025 · 7
SOPRAVVENUTE ESIGENZE NORMATIVE E REGOLAMENTARI
Approved on 13 Aug 2025 · 7
SOPRAVVENUTE ESIGENZE NORMATIVE E REGOLAMENTARI
Approved on 13 Aug 2025 · 7
PERIZIA DI VARIANTE TECNICA AI SENSI DELL''ART. 106 COMMA 1 LETT. C.1 DEL D.LGS. 50/2016
Approved on 24 Aug 2023 · 99
Suspensions
CAUSE DI FORZA MAGGIORE
From 23 Dec 2024 · resumed on 9 Jan 2025
CAUSE DI FORZA MAGGIORE
From 23 Dec 2024 · resumed on 9 Jan 2025
CAUSE DI FORZA MAGGIORE
From 23 Dec 2024 · resumed on 9 Jan 2025
INTERFERENZE DI NATURA TECNICA
From 5 Feb 2024 · resumed on 8 Jul 2024
INTERFERENZE DI NATURA TECNICA
From 5 Feb 2024 · resumed on 8 Jul 2024
INTERFERENZE DI NATURA TECNICA
From 5 Feb 2024 · resumed on 8 Jul 2024
REDAZIONE DI VARIANTI IN CORSO DI ESECUZIONE
From 21 Jul 2023 · resumed on 30 Aug 2023
REDAZIONE DI VARIANTI IN CORSO DI ESECUZIONE
From 21 Jul 2023 · resumed on 30 Aug 2023
REDAZIONE DI VARIANTI IN CORSO DI ESECUZIONE
From 21 Jul 2023 · resumed on 30 Aug 2023
Progress step 1
Issued 5 Jun 2023 · €832,932 · delay flagged
Progress step 2
Issued 18 Jun 2024 · €95,600 · delay flagged
Progress step 3
Issued 28 Feb 2025 · €611,692 · delay flagged
Progress step 4
Issued 16 Oct 2025 · €1,283,513 · delay flagged
Progress step 5
Issued 31 Mar 2026 · €2,316,192 · payment certified 30 Apr 2026 · delay flagged
Loading comparison…
Single bidder — In sector Construction works in Lombardy, 10.7% of comparable tenders drew at least 3 bidders (of 49549 tenders). The score alone does not say whether that is unusual; this context does.
10.7% of comparable tenders had ≥3 bidders (n=49549)
Loading…
Loading…
Loading…
Source data & verification
ANAC BDNCP — dati tabellari
Verify on ANACIngested: 20 Sept 2026
Release: 20260801-cig_csv.csv
Days to submit bids: 54