LAVORI DI RICOSTRUZIONE DEL MANTO STRADALE DI ALCUNE STRADE INTERNE AL CENTRO ABITATO
COMUNE DI RUFFANO
Amount
Award date
Bids
Published
Estimated tender value
Sector (CPV)
Loading actions…
Publication / start of procedure
28 Aug 2020
Step completedTime to submit bids
8 Sept 2020
11 days between opening and deadline
Step completedAward
15 Sept 2020
Step completedContract variation
29 Dec 2020
Step completedWork suspension
6 May 2021
These are automated checks on public data. They help you decide what to look into — they are not criminal findings.
This contract triggered 6 pattern(s) worth a closer look:
Tight deadlines · Near legal threshold
- Very short bid submission period What does this mean?
- Amount near regulatory threshold (possible contract splitting) What does this mean?
- Repeated awards to the same supplier (same CA, 12 months) What does this mean?
- Publish or award date near an election date (temporal pattern) What does this mean?
- Contract variation recorded on ANAC What does this mean?
- Work suspension recorded What does this mean?
| Supplier | Region | Amount | Award date | Status |
|---|---|---|---|---|
| IMPRESTRADE DI CACCIATORE COSIMO | — | €139,300 | 15 Sept 2020 | AGGIUDICATA |
Variations
RINVENIMENTI NON PREVEDIBILI AL MOMENTO DELLA REDAZIONE DEL PROGETTO
Approved on 29 Dec 2020 · 99
Suspensions
CAUSE DI FORZA MAGGIORE
From 6 May 2021 · resumed on 2 Jun 2021
AVVERSE CONDIZIONI CLIMATICHE
From 21 Jan 2021 · resumed on 26 Apr 2021
REDAZIONE DI VARIANTI IN CORSO DI ESECUZIONE
From 4 Nov 2020 · resumed on 11 Jan 2021
AVVERSE CONDIZIONI CLIMATICHE
From 27 Oct 2020 · resumed on 2 Nov 2020
AVVERSE CONDIZIONI CLIMATICHE
From 12 Oct 2020 · resumed on 16 Oct 2020
AVVERSE CONDIZIONI CLIMATICHE
From 6 Oct 2020 · resumed on 9 Oct 2020
Loading comparison…
Loading…
Loading…
Source data & verification
ANAC BDNCP — dati tabellari
Verify on ANACIngested: 5 Aug 2026
Release: 20260401-cig_csv.csv
Days to submit bids: 11