PROCEDURA APERTA PER LA REALIZZAZIONE DI NUOVO FABBRICATO DI EDILIZIA RESIDENZIALE PUBBLICA PER 31 ALLOGGI IN LOCALITÀ I POGGI, COMUNE DI MASSA (MS)
EDILIZIA RESIDENZIALE PUBBLICA MASSA CARRARA SPA
Amount
Award date
Bids
Published
Estimated tender value
Applicable legal ceiling
National maximum for this procedure type under D.Lgs 36/2023 — verify on official sources.
Award vs estimate
Sector
Loading actions…
Publication / start of procedure
25 Oct 2017
Step completedTime to submit bids
14 Nov 2017
20 days between opening and deadline
Step completedAward
19 Sept 2018
Step completedContract signed
7 Dec 2018
Step completedContract variation
28 Mar 2023
Step completedWork suspension
22 Mar 2020
Step completedWorks progress (SAL)
8 Jun 2026
Loading…
These are automated checks on public data. They help you decide what to look into — they are not criminal findings.
This contract triggered 6 pattern(s) worth a closer look:
Variation on record · Multiple variations
- Contract variation recorded on ANAC What does this mean?
- Multiple variations on the same contract What does this mean?
- Work suspension recorded What does this mean?
- Discount very different from similar tenders What does this mean?
- Works delayed (SAL) What does this mean?
- No closure recorded
Tuscany · More tenders in this area
AUSA code: 0000172961
CARRARA
Authority profile| Supplier | Region | Amount | Award date | Status |
|---|---|---|---|---|
| IMPREGEGA SRL | — | €2,190,801 | 19 Sept 2018 | AGGIUDICATA |
| CEMIP SOCIETA' A RESPONSABILITA' LIMITATA | — | €2,190,801 | 19 Sept 2018 | AGGIUDICATA |
| BOLOGNA & PONZANELLI S.R.L. | — | €2,190,801 | 19 Sept 2018 | AGGIUDICATA |
| Organisation | Role | Outcome |
|---|---|---|
| BOLOGNA & PONZANELLI S.R.L. 00059670117 | Not reported | Awarded |
| CEMIP SOCIETA' A RESPONSABILITA' LIMITATA 01195650104 | Not reported | Awarded |
| IMPREGEGA SRL 01264840453 | Not reported | Awarded |
Variations
ALTRE MODIFICHE DI IMPORTO INFERIORE ALLA SOGLIA COMUNITARIA E AL 10% DEL VALORE CONTRATTUALE PER SERVIZI E FORNITURE O AL 15% PER LAVORI
Approved on 28 Mar 2023 · 16
ALTRE MODIFICHE DI IMPORTO INFERIORE ALLA SOGLIA COMUNITARIA E AL 10% DEL VALORE CONTRATTUALE PER SERVIZI E FORNITURE O AL 15% PER LAVORI
Approved on 20 Jun 2022 · 16
Suspensions
CAUSE DI FORZA MAGGIORE
From 22 Mar 2020 · resumed on 11 May 2020
CAUSE DI FORZA MAGGIORE
From 22 Mar 2020 · resumed on 11 May 2020
REDAZIONE DI VARIANTI IN CORSO DI ESECUZIONE
From 29 Apr 2019 · resumed on 31 Jul 2019
REDAZIONE DI VARIANTI IN CORSO DI ESECUZIONE
From 29 Apr 2019 · resumed on 31 Jul 2019
INTERFERENZE DI NATURA AMMINISTRATIVA
From 29 Mar 2019 · resumed on 9 Apr 2019
INTERFERENZE DI NATURA AMMINISTRATIVA
From 29 Mar 2019 · resumed on 9 Apr 2019
SAL N. 1 LAVORI A TUTTO IL 18/12/2019
Issued 18 Dec 2019 · €219,514 · payment certified 18 Dec 2019 · delay flagged
SAL N. 2
Issued 27 Oct 2020 · €472,733 · payment certified 27 Oct 2020 · delay flagged
SAL N. 3
Issued 29 Apr 2021 · €800,217 · payment certified 29 Apr 2021 · delay flagged
SAL 04
Issued 1 Aug 2022 · €959,085 · payment certified 1 Aug 2022 · delay flagged
SAL N. 5
Issued 17 Feb 2023 · €1,121,169 · payment certified 23 Feb 2023 · delay flagged
SAL N. 6
Issued 20 Apr 2023 · €1,272,016 · payment certified 26 Apr 2023 · delay flagged
SAL N. 4 (CP 4BIS DI COMPENSAZIONE)
Issued 1 Aug 2022 · €959,085 · payment certified 23 May 2023 · delay flagged
SAL 5 (CP 5BIS - COMPENSAZIONE)
Issued 17 Feb 2023 · €1,121,169 · payment certified 26 May 2023 · delay flagged
SAL N. 6 - CP6BIS
Issued 20 Apr 2023 · €1,272,016 · payment certified 12 Jan 2024 · delay flagged
SAL N. 8
Issued 29 Feb 2024 · €1,594,148 · payment certified 29 Feb 2024 · delay flagged
SAL N. 8 - CP 8 BIS ADEGUAMENTO PREZZI
Issued 29 Feb 2024 · €1,594,148 · payment certified 19 Mar 2024 · delay flagged
SAL N. 7 - CP 7BIS
Issued 9 Nov 2023 · €1,447,549 · payment certified 12 Jan 2024 · delay flagged
SAL N. 9
Issued 18 Apr 2024 · €1,744,715 · payment certified 19 Apr 2024 · delay flagged
SAL N. 9 - CP 9 BIS
Issued 18 Apr 2024 · €1,744,715 · payment certified 6 Jun 2024 · delay flagged
SAL N. 10 CON CP 10
Issued 1 Jul 2024 · €1,810,115 · payment certified 1 Jul 2024 · delay flagged
CP N. 10 BIS RELATIVO A SAL N. 10 COMPENSAZIONE DEI PREZZI (VEDI PROT. 11569 DEL 09.08.2024)
Issued 1 Jul 2024 · €1,810,115 · payment certified 1 Aug 2024 · delay flagged
SAL N. 11 E CP 11 - VEDI PROT. 11571 DEL 09.08.2024
Issued 1 Aug 2024 · €1,886,818 · payment certified 1 Aug 2024 · delay flagged
CP 11 BIS SU SAL N. 11 PER COMPENSAZIONE PREZZI - (VEDI PROT. 11573 DEL 09.08.2024)
Issued 1 Aug 2024 · €1,886,818 · payment certified 1 Aug 2024 · delay flagged
SAL N. 12 E CP 12
Issued 25 Oct 2024 · €1,988,193 · payment certified 22 Nov 2024 · delay flagged
SAL N. 12 CON CP 12 BIS COMPENSAZIONE PREZZI
Issued 25 Oct 2024 · €1,988,193 · payment certified 22 Nov 2024 · delay flagged
SAL N. 13 CON CP 13
Issued 7 Apr 2025 · €2,156,147 · payment certified 22 Apr 2025 · delay flagged
SAL N. 13 CON CP 13 COMPENSAZIONE PREZZI
Issued 7 Apr 2025 · €2,156,147 · payment certified 22 Apr 2025 · delay flagged
SAL N. 14 CON CP 14
Issued 8 Jun 2026 · €2,216,511 · payment certified 18 Jun 2026 · delay flagged
Loading comparison…
In sector Construction works in Tuscany, 12.0% of comparable tenders drew at least 3 bidders (of 30271 tenders).
12% of comparable tenders had ≥3 bidders (n=30271)
Loading…
Loading…
Loading…
Source data & verification
ANAC BDNCP — dati tabellari
Verify on ANACIngested: 20 Sept 2026
Release: 20260801-cig_csv.csv
Days to submit bids: 20