AUTOSTRADA DEI TRAFORI ALPINI (A26) - TRATTO: BIVIO A10 - MASONE - PIANO SICUREZZA GALLERIE EX D.LGS. 264/06- FASE 2 - LOTTO 4B - GALLERIE MANFREIDA, DI CASA MONACCHI, MASSIMO RISSO, TURCHINO, BERTE'
AUTOSTRADE PER L'ITALIA S.P.A.
Amount
Award date
Bids
Published
Estimated tender value
Applicable legal ceiling
National maximum for this procedure type under D.Lgs 36/2023 — verify on official sources.
Award vs estimate
Sector
Loading actions…
2019 European election · 26 May 2019
27 days after the election date on record.
Publication / start of procedure
11 Oct 2017
Step completedTime to submit bids
23 Nov 2017
43 days between opening and deadline
Step completedAward
29 Apr 2019
Step completedContract signed
5 Nov 2019
Step completedContract variation
28 May 2025
Step completedWorks progress (SAL)
30 Nov 2025
Loading…
These are automated checks on public data. They help you decide what to look into — they are not criminal findings.
This contract triggered 6 pattern(s) worth a closer look:
Same supplier often · Near elections — worth reviewing
- Repeated awards to the same supplier (same CA, 12 months) What does this mean?
- Publish or award date near an election date (temporal pattern) What does this mean?
- Discount very different from similar tenders What does this mean?
- Works delayed (SAL) What does this mean?
- No start recorded
- Funding source not reported
Lazio · More tenders in this area
AUSA code: 0000231595
ROMA
Authority profile| Supplier | Region | Amount | Award date | Status |
|---|---|---|---|---|
| MANCINO S.R.L. | — | €6,072,315 | 29 Apr 2019 | AGGIUDICATA |
| SOITEK S.R.L. | — | €6,072,315 | 29 Apr 2019 | AGGIUDICATA |
| NEOCOS S.R.L. | — | €6,072,315 | 29 Apr 2019 | AGGIUDICATA |
| Organisation | Role | Outcome |
|---|---|---|
| MANCINO S.R.L. 03105390961 | MANDANTE | Awarded |
| NEOCOS S.R.L. 01128640032 | MANDATARIA | Awarded |
| SOITEK S.R.L. 02260540840 | MANDANTE | Awarded |
Variations
ART. 26 D.L. N. 50 DEL 17/05/2022
Approved on 28 May 2025 · 99
REVISIONE DEI PREZZI
Approved on 28 May 2024 · 22
ART. 106, COMMA 1, LETT. C) DEL D.LGS. 50/2016 S.M.I.
Approved on 27 Feb 2023 · 99
MODIFICHE PREVISTE DAI DOCUMENTI DI GARA INIZIALI
Approved on 29 Apr 2022 · 17
ALTRE CAUSE IMPREVISTE ED IMPREVEDIBILI
Approved on 29 Apr 2022 · 8
Progress step 1
Issued 5 Nov 2019 · €0 · payment certified 10 Jan 2020 · delay flagged
SAL 2
Issued 18 Dec 2019 · €0 · payment certified 10 Jan 2020 · delay flagged
SAL 3
Issued 3 Mar 2020 · €0 · payment certified 27 Apr 2020 · delay flagged
SAL 4
Issued 26 May 2020 · €563,748 · payment certified 10 Jun 2020 · delay flagged
SAL 5
Issued 16 Jul 2020 · €575,391 · payment certified 27 Jul 2020 · delay flagged
SAL 6
Issued 31 Jul 2020 · €316,393 · payment certified 24 Aug 2020 · delay flagged
SAL 7
Issued 11 Nov 2020 · €134,755 · payment certified 16 Dec 2020 · delay flagged
SAL 8
Issued 25 Nov 2020 · €338,329 · payment certified 1 Feb 2021 · delay flagged
SAL N.9 A TUTTO IL 25/01/2021
Issued 25 Jan 2021 · €2,180,929 · payment certified 18 Mar 2021 · delay flagged
SAL N. 10 A TUTTO IL 25/03/2021
Issued 25 Mar 2021 · €2,664,488 · payment certified 20 May 2021 · delay flagged
SAL N.11 A TUTTO IL 25/05/2021
Issued 25 May 2021 · €3,198,550 · payment certified 21 Jul 2021 · delay flagged
SAL N. 12 A TUTTO IL 15/06/2021
Issued 15 Jun 2021 · €3,336,836 · payment certified 26 Jul 2021 · delay flagged
SAL N. 13 A TUTTO IL 25/07/2021
Issued 25 Jul 2021 · €3,729,825 · payment certified 23 Sept 2021 · delay flagged
SAL 14 A TUTTO IL 25.09.2021
Issued 25 Sept 2021 · €4,074,343 · payment certified 16 Nov 2021 · delay flagged
SAL N. 15 A TUTTO IL 25/11/2021
Issued 25 Nov 2021 · €5,015,701 · payment certified 18 Jan 2022 · delay flagged
SAL N. 16 A TUTTO IL 25/01/2022
Issued 25 Jan 2022 · €5,731,826 · payment certified 31 Mar 2022 · delay flagged
SAL N 17 A TUTTO IL 25/3
Issued 25 Mar 2022 · €6,504,285 · payment certified 9 Jun 2022 · delay flagged
SAL N. 18 A TUTTO IL 25/05/2022
Issued 25 May 2022 · €7,007,938 · payment certified 12 Sept 2022 · delay flagged
SAL N. 19 A TUTTO IL 25/05/2022-ART. 26
Issued 25 May 2022 · €7,007,938 · payment certified 12 Sept 2022 · delay flagged
SAL N. 20 A TUTTO IL 30/11/2022-ORDINARIO+ART. 26
Issued 30 Nov 2022 · €7,940,928 · payment certified 9 Jan 2023 · delay flagged
CDP RIF. SAP 22 A TUTTO IL 31.01.2023
Issued 31 Jan 2023 · €8,429,481 · payment certified 9 Mar 2023 · delay flagged
CDP RIF. ASPI 23 A TUTTO IL 31/03/2023
Issued 31 Mar 2023 · €8,761,273 · payment certified 26 Jun 2023 · delay flagged
CDP RIF. ASPI 24 A TUTTO IL 31/05/2023
Issued 31 May 2023 · €9,461,775 · payment certified 28 Aug 2023 · delay flagged
CDP RIF. ASPI 25 A TUTTO IL 31/07/2023
Issued 31 Jul 2023 · €9,803,540 · payment certified 11 Oct 2023 · delay flagged
CDP RIF ASPI 26 A TUTTO IL 31/05/2024
Issued 31 May 2024 · €10,591,091 · payment certified 10 Jul 2024 · delay flagged
CDP RIF. ASPI 27 A TUTTO IL 30/11/2024
Issued 30 Nov 2024 · €10,680,154 · payment certified 22 Jan 2025 · delay flagged
CDP RIF. ASPI 28 A TUTTO IL 31/03/2025
Issued 31 Mar 2025 · €10,755,483 · payment certified 3 Aug 2025 · delay flagged
CDP RIF. ASPI 29 A TUTTO IL 30/11/2025
Issued 30 Nov 2025 · €11,014,092 · payment certified 28 Jan 2026 · delay flagged
Loading comparison…
In sector Construction works in Liguria, 9.7% of comparable tenders drew at least 3 bidders (of 12716 tenders).
9.7% of comparable tenders had ≥3 bidders (n=12716)
Loading…
Loading…
Loading…
Source data & verification
ANAC BDNCP — dati tabellari
Verify on ANACIngested: 5 Aug 2026
Release: 20260401-cig_csv.csv
Days to submit bids: 43