FONDAZIONE TEATRO DONIZETTI DI BERGAMO
Amount
Award date
Bids
Published
Estimated tender value
Applicable legal ceiling
National maximum for this procedure type under D.Lgs 36/2023 — verify on official sources.
Award vs estimate
Sector
Loading actions…
Publication / start of procedure
16 Jun 2017
Step completedTime to submit bids
3 Aug 2017
48 days between opening and deadline
Step completedAward
29 Nov 2017
Step completedContract signed
20 Jun 2018
Step completedContract variation
10 Jul 2019
Step completedWork suspension
13 Mar 2020
Step completedWorks progress (SAL)
30 Oct 2020
Loading…
These are automated checks on public data. They help you decide what to look into — they are not criminal findings.
This contract triggered 8 pattern(s) worth a closer look:
Variation on record · Multiple variations
Lombardy · More tenders in this area
AUSA code: 0000561051
BERGAMO
Authority profile| Supplier | Region | Amount | Award date | Status |
|---|---|---|---|---|
| FANTINO COSTRUZIONI S.P.A. | — | €11,087,531 | 29 Nov 2017 | AGGIUDICATA |
| NOTARIMPRESA S.P.A. | — | €11,087,531 | 29 Nov 2017 | AGGIUDICATA |
| Organisation | Role | Outcome |
|---|---|---|
| FANTINO COSTRUZIONI S.P.A. 00293940045 | MANDATARIA | Awarded |
| NOTARIMPRESA S.P.A. 00129050035 | MANDANTE | Awarded |
Variations
ART.132 C.1 LETT. C) D.LGS.163/2006
Approved on 10 Jul 2019 · 3
ART.132 C.1 LETT. B) D.LGS.163/2006
Approved on 24 Jul 2018 · 2
Suspensions
CAUSE DI FORZA MAGGIORE
From 13 Mar 2020 · resumed on 4 May 2020
CAUSE DI FORZA MAGGIORE
From 13 Mar 2020 · resumed on 4 May 2020
PUBBLICO INTERESSE O NECESSITA'
From 31 Oct 2019 · resumed on 25 Nov 2019
PUBBLICO INTERESSE O NECESSITA'
From 31 Oct 2019 · resumed on 25 Nov 2019
Progress step 1
Issued 20 Jun 2018 · €1,313,028 · payment certified 24 Jul 2018 · delay flagged
Progress step 2
Issued 21 Sept 2018 · €2,589,679 · payment certified 16 Oct 2018 · delay flagged
Progress step 3
Issued 28 Dec 2018 · €3,851,608 · payment certified 4 Feb 2019 · delay flagged
Progress step 4
Issued 28 Feb 2019 · €5,112,063 · payment certified 4 Apr 2019 · delay flagged
Progress step 5
Issued 28 May 2019 · €6,372,392 · payment certified 5 Jun 2019 · delay flagged
Progress step 6
Issued 30 Jul 2019 · €7,646,016 · payment certified 7 Aug 2019 · delay flagged
Progress step 7
Issued 24 Oct 2019 · €8,907,585 · payment certified 21 Nov 2019 · delay flagged
Progress step 8
Issued 31 Jan 2020 · €10,169,212 · payment certified 20 Feb 2020 · delay flagged
Progress step 9
Issued 23 Mar 2020 · €10,738,715 · payment certified 6 May 2020 · delay flagged
Progress step 10
Issued 12 Sept 2020 · €10,567,500 · payment certified 8 Oct 2020 · delay flagged
Progress step 11
Issued 3 Jul 2020 · €9,556,500 · payment certified 12 Aug 2020 · delay flagged
Progress step 12
Issued 30 Oct 2020 · €11,570,200 · payment certified 15 Jan 2021 · delay flagged
Loading comparison…
In sector Construction works in Lombardy, 11.3% of comparable tenders drew at least 3 bidders (of 51978 tenders).
11.3% of comparable tenders had ≥3 bidders (n=51978)
Loading…
Loading…
Loading…
ANAC BDNCP — dati tabellari
Verify on ANACIngested: 5 Aug 2026
Release: 20260401-cig_csv.csv
Days to submit bids: 48