CONCESSIONE PER LA GESTIONE DELLE PISCINE DI PROPRIETÀ REGIONALE

REGIONE AUTONOMA VALLE D'AOSTA

CIG 6976659921Verify on ANACAosta ValleyServicesCulture, sport and recreationOpen procedureCode 92610000-0Risk signal — not an accusation of crime.
At a glance
Key figures from open ANAC records for this contract.

Amount

€5,447,111

Award date

19 Jun 2017

Bids

1

Published

29 Mar 2017

Estimated tender value

€5,746,661

Applicable legal ceiling

€140,000

National maximum for this procedure type under D.Lgs 36/2023 — verify on official sources.

Award vs estimate

-5.2%

Sector

Culture, sport and recreationSERVIZI DI GESTIONE DI IMPIANTI SPORTIVI
How do I verify this tender?

Loading actions…

Timeline
  1. Publication / start of procedure

    29 Mar 2017

    Step completed
  2. Time to submit bids

    2 May 2017

    34 days between opening and deadline

    Step completed
  3. Award

    19 Jun 2017

    Step completed
  4. Contract signed

    1 Sept 2017

    Step completed
  5. Contract variation

    26 Jan 2026

    Step completed
  6. Works progress (SAL)

    3 Aug 2026

Delivery record

Loading…

In plain language

These are automated checks on public data. They help you decide what to look into — they are not criminal findings.

This contract triggered 5 pattern(s) worth a closer look:

Low competition · Discount very different from similar tenders

Contracting authority (buyer)
Awarded to (suppliers)
1 award line(s) on record.
SupplierRegionAmountAward dateStatus
AOSTA CALCIO 511 SOCIETA' SPORTIVA DILETTANTISTICA A RESPONSABILITA' LIMITATA€5,447,11119 Jun 2017AGGIUDICATA
Who took part
2 participant(s) recorded on ANAC (not only the winner).
What happened after the award
Variations and suspensions recorded on ANAC — read them with the signals, not as an accusation.

Variations

  • MODIFICHE PREVISTE DAL CONTRATTO - ADEGUAMENTO ISTAT - ART 106 C. 1 LETT A) DEL 50/2016

    Approved on 26 Jan 2026 · 99

  • MODIFICHE PREVISTE DAL CONTRATTO - ADEGUAMENTO ISTAT - ART 106 C. 1 LETT A) DEL 50/2016

    Approved on 21 Jan 2025 · 99

  • MODIFICHE PREVISTE DAL CONTRATTO - ADEGUAMENTO ISTAT - ART 106 C. 1 LETT A) DEL 50/2016

    Approved on 16 Jan 2024 · 99

  • ECCEZIONALE AUMENTO DEI PREZZI DELLE COMPONENTI ENERGETICHE

    Approved on 17 Oct 2023 · 99

  • MODIFICHE PREVISTE DAI DOCUMENTI DI GARA INIZIALI

    Approved on 24 Mar 2023 · 17

  • ADEGUAMENTO ISTAT 2022 (ART. 160, COMMA 1 LETTERA A)

    Approved on 6 Feb 2023 · 99

  • CORRISPETTIVO STRAORDINARIO PER CARO ENERGIA (ANNO 2022)

    Approved on 9 Dec 2022 · 99

  • ADEGUAMENTO ISTAT 2022 (ART. 160, COMMA 1 LETTERA A))

    Approved on 13 Jan 2022 · 99

  • ADEGUAMENTO ISTAT 2021 (ART. 160, COMMA 1 LETTERA A))

    Approved on 28 Jan 2021 · 99

  • ADEGUAMENTO ISTAT 2019 (ART. 160, COMMA 1 LETTERA A))

    Approved on 17 Jan 2019 · 99

  • NON EFFETTUAZIONE DEI LAVORI DI EFFICIENTAMENTO DELLA PISCINA DI PRÉ-SAINT-DIDIER

    Approved on 28 Mar 2018 · 99

Works progress (SAL)
Progress certificates (stati di avanzamento) from ANAC — amounts and delays as published.
  • Progress step 1

    Issued 2 Nov 2022 · €2,423,355 · delay flagged

  • Progress step 2

    Issued 13 Oct 2022 · €2,390,612 · delay flagged

  • Progress step 3

    Issued 13 Oct 2022 · €2,338,847 · delay flagged

  • Progress step 4

    Issued 1 Sept 2022 · €2,306,105 · delay flagged

  • Progress step 5

    Issued 2 Aug 2022 · €2,273,363 · delay flagged

  • Progress step 6

    Issued 4 Jul 2022 · €2,240,620 · delay flagged

  • Progress step 7

    Issued 1 Jun 2022 · €2,207,878 · delay flagged

  • Progress step 8

    Issued 2 May 2022 · €2,175,136 · delay flagged

  • Progress step 9

    Issued 8 Apr 2022 · €2,142,394 · delay flagged

  • Progress step 10

    Issued 1 Apr 2022 · €2,099,215 · delay flagged

  • Progress step 11

    Issued 1 Mar 2022 · €2,066,473 · delay flagged

  • Progress step 12

    Issued 3 Feb 2022 · €2,033,731 · delay flagged

  • Progress step 13

    Issued 17 Jan 2022 · €2,000,989 · delay flagged

  • Progress step 14

    Issued 10 Dec 2021 · €1,968,247 · delay flagged

  • Progress step 15

    Issued 12 Nov 2021 · €1,936,458 · delay flagged

  • Progress step 16

    Issued 12 Nov 2021 · €1,904,670 · delay flagged

  • Progress step 17

    Issued 15 Oct 2021 · €1,859,041 · delay flagged

  • Progress step 18

    Issued 12 Oct 2021 · €1,819,729 · delay flagged

  • Progress step 19

    Issued 1 Sept 2021 · €1,787,941 · delay flagged

  • Progress step 20

    Issued 1 Sept 2021 · €1,756,152 · delay flagged

  • Progress step 21

    Issued 3 Aug 2021 · €1,734,152 · delay flagged

  • Progress step 22

    Issued 1 Jul 2021 · €1,702,517 · delay flagged

  • Progress step 23

    Issued 1 Jul 2021 · €1,670,601 · delay flagged

  • Progress step 24

    Issued 20 May 2021 · €1,664,218 · delay flagged

  • Progress step 25

    Issued 11 May 2021 · €1,642,218 · delay flagged

  • Progress step 26

    Issued 18 Feb 2021 · €1,620,218 · delay flagged

  • Progress step 27

    Issued 21 Jan 2021 · €1,613,691 · delay flagged

  • Progress step 28

    Issued 21 Jan 2021 · €1,590,591 · delay flagged

  • Progress step 29

    Issued 2 Dec 2020 · €1,579,591 · delay flagged

  • Progress step 30

    Issued 4 Nov 2020 · €1,556,247 · delay flagged

  • Progress step 31

    Issued 23 Oct 2020 · €1,529,650 · delay flagged

  • Progress step 32

    Issued 1 Oct 2020 · €1,474,650 · delay flagged

  • Progress step 33

    Issued 10 Sept 2020 · €1,442,734 · delay flagged

  • Progress step 34

    Issued 1 Sept 2020 · €1,417,861 · delay flagged

  • Progress step 35

    Issued 7 Aug 2020 · €1,385,945 · delay flagged

  • Progress step 36

    Issued 9 Jul 2020 · €1,354,029 · delay flagged

  • Progress step 37

    Issued 8 Jun 2020 · €1,322,113 · delay flagged

  • Progress step 38

    Issued 9 Apr 2020 · €1,293,388 · delay flagged

  • Progress step 39

    Issued 2 Mar 2020 · €1,283,813 · delay flagged

  • Progress step 40

    Issued 3 Feb 2020 · €1,251,897 · delay flagged

  • Progress step 41

    Issued 9 Jan 2020 · €1,219,981 · delay flagged

  • Progress step 42

    Issued 9 Jan 2020 · €1,188,065 · delay flagged

  • Progress step 43

    Issued 2 Dec 2019 · €1,158,365 · delay flagged

  • Progress step 44

    Issued 25 Nov 2019 · €1,126,449 · delay flagged

  • Progress step 45

    Issued 4 Nov 2019 · €1,050,414 · delay flagged

  • Progress step 46

    Issued 3 Oct 2019 · €1,018,498 · delay flagged

  • Progress step 47

    Issued 2 Sept 2019 · €986,582 · delay flagged

  • Progress step 48

    Issued 6 Aug 2019 · €954,666 · delay flagged

  • Progress step 49

    Issued 4 Jul 2019 · €922,750 · delay flagged

  • Progress step 50

    Issued 7 Jun 2019 · €890,833 · delay flagged

  • Progress step 51

    Issued 15 May 2019 · €858,917 · delay flagged

  • Progress step 52

    Issued 20 May 2019 · €811,917 · delay flagged

  • Progress step 53

    Issued 7 May 2019 · €798,186 · delay flagged

  • Progress step 54

    Issued 15 Apr 2019 · €766,270 · delay flagged

  • Progress step 55

    Issued 1 Mar 2019 · €734,354 · delay flagged

  • Progress step 56

    Issued 21 Feb 2019 · €702,438 · delay flagged

  • Progress step 57

    Issued 5 Feb 2019 · €642,438 · delay flagged

  • Progress step 58

    Issued 8 Jan 2019 · €610,522 · delay flagged

  • Progress step 59

    Issued 21 Dec 2018 · €578,606 · delay flagged

  • Progress step 60

    Issued 6 Dec 2018 · €518,606 · delay flagged

  • Progress step 61

    Issued 15 Nov 2018 · €487,161 · delay flagged

  • Progress step 62

    Issued 15 Oct 2018 · €455,717 · delay flagged

  • Progress step 63

    Issued 5 Oct 2018 · €453,692 · delay flagged

  • Progress step 64

    Issued 3 Sept 2018 · €422,247 · delay flagged

  • Progress step 65

    Issued 3 Aug 2018 · €399,076 · delay flagged

  • Progress step 66

    Issued 2 Aug 2018 · €382,114 · delay flagged

  • Progress step 67

    Issued 1 Jun 2018 · €352,260 · delay flagged

  • Progress step 68

    Issued 4 Jun 2018 · €312,154 · delay flagged

  • Progress step 69

    Issued 15 May 2018 · €265,825 · delay flagged

  • Progress step 70

    Issued 2 Mar 2018 · €219,496 · delay flagged

  • Progress step 71

    Issued 2 Feb 2018 · €188,174 · delay flagged

  • Progress step 72

    Issued 5 Jan 2018 · €156,853 · delay flagged

  • Progress step 73

    Issued 5 Dec 2017 · €125,532 · delay flagged

  • Progress step 74

    Issued 2 Nov 2017 · €94,210 · payment certified 15 Nov 2017 · delay flagged

  • Progress step 75

    Issued 2 Oct 2017 · €62,889 · payment certified 7 Nov 2017 · delay flagged

  • Progress step 76

    Issued 1 Sept 2017 · €31,444 · payment certified 7 Nov 2017 · delay flagged

  • Progress step 77

    Issued 1 Dec 2022 · €2,456,097 · delay flagged

  • Progress step 78

    Issued 9 Dec 2022 · €2,546,097 · delay flagged

  • Progress step 79

    Issued 13 Jan 2023 · €2,582,604 · delay flagged

  • Progress step 80

    Issued 1 Feb 2023 · €2,619,111 · delay flagged

  • Progress step 81

    Issued 21 Mar 2023 · €2,660,878 · delay flagged

  • Progress step 82

    Issued 22 Mar 2023 · €2,697,385 · delay flagged

  • Progress step 83

    Issued 3 Apr 2023 · €2,731,700 · delay flagged

  • Progress step 84

    Issued 27 Apr 2023 · €2,761,752 · delay flagged

  • Progress step 85

    Issued 2 May 2023 · €2,796,067 · delay flagged

  • Progress step 86

    Issued 1 Jun 2023 · €2,830,382 · delay flagged

  • Progress step 87

    Issued 4 Jul 2023 · €2,864,697 · delay flagged

  • Progress step 88

    Issued 1 Aug 2023 · €2,899,011 · delay flagged

  • Progress step 89

    Issued 1 Sept 2023 · €2,933,326 · delay flagged

  • Progress step 90

    Issued 17 Oct 2023 · €2,989,326 · delay flagged

  • Progress step 91

    Issued 18 Oct 2023 · €3,023,641 · delay flagged

  • Progress step 92

    Issued 26 Oct 2023 · €3,099,925 · delay flagged

  • Progress step 93

    Issued 3 Nov 2023 · €3,134,240 · delay flagged

  • Progress step 94

    Issued 4 Dec 2023 · €3,168,555 · delay flagged

  • Progress step 95

    Issued 4 Jan 2024 · €3,202,869 · delay flagged

  • Progress step 96

    Issued 1 Feb 2024 · €3,239,522 · delay flagged

  • Progress step 97

    Issued 1 Mar 2024 · €3,275,554 · delay flagged

  • Progress step 98

    Issued 4 Mar 2024 · €3,309,023 · delay flagged

  • Progress step 99

    Issued 2 Apr 2024 · €3,345,055 · delay flagged

  • Progress step 100

    Issued 2 May 2024 · €3,381,086 · delay flagged

  • Progress step 101

    Issued 3 May 2024 · €3,416,288 · delay flagged

  • Progress step 102

    Issued 3 Jun 2024 · €3,453,416 · delay flagged

  • Progress step 103

    Issued 1 Jul 2024 · €3,490,544 · delay flagged

  • Progress step 104

    Issued 1 Aug 2024 · €3,527,672 · delay flagged

  • Progress step 105

    Issued 2 Sept 2024 · €3,564,800 · delay flagged

  • Progress step 106

    Issued 1 Oct 2024 · €3,601,928 · delay flagged

  • Progress step 107

    Issued 21 Oct 2024 · €3,660,569 · delay flagged

  • Progress step 108

    Issued 4 Nov 2024 · €3,697,697 · delay flagged

  • Progress step 109

    Issued 2 Dec 2024 · €3,734,825 · delay flagged

  • Progress step 110

    Issued 2 Jan 2025 · €3,771,953 · delay flagged

  • Progress step 111

    Issued 3 Feb 2025 · €3,828,312 · delay flagged

  • Progress step 112

    Issued 3 Mar 2025 · €3,847,100 · delay flagged

  • Progress step 113

    Issued 1 Apr 2025 · €3,884,525 · delay flagged

  • Progress step 114

    Issued 2 May 2025 · €3,921,950 · delay flagged

  • Progress step 115

    Issued 13 May 2025 · €3,956,504 · delay flagged

  • Progress step 116

    Issued 3 Jun 2025 · €3,993,929 · delay flagged

  • Progress step 117

    Issued 1 Jul 2025 · €4,031,354 · delay flagged

  • Progress step 118

    Issued 13 Aug 2025 · €4,068,779 · delay flagged

  • Progress step 119

    Issued 1 Sept 2025 · €4,106,204 · delay flagged

  • Progress step 120

    Issued 9 Sept 2025 · €4,154,944 · delay flagged

  • Progress step 121

    Issued 1 Oct 2025 · €4,192,369 · delay flagged

  • Progress step 122

    Issued 11 Nov 2025 · €4,229,794 · delay flagged

  • Progress step 123

    Issued 1 Dec 2025 · €4,267,219 · delay flagged

  • Progress step 124

    Issued 18 Dec 2025 · €4,316,521 · delay flagged

  • Progress step 125

    Issued 2 Jan 2026 · €4,353,946 · delay flagged

  • Progress step 126

    Issued 2 Feb 2026 · €4,392,194 · delay flagged

  • Progress step 127

    Issued 2 Mar 2026 · €4,447,942 · delay flagged

  • Progress step 128

    Issued 2 Apr 2026 · €4,503,689 · delay flagged

  • Progress step 129

    Issued 30 Apr 2026 · €4,559,436 · delay flagged

  • Progress step 130

    Issued 12 May 2026 · €4,574,199 · delay flagged

  • Progress step 131

    Issued 21 May 2026 · €4,614,361 · delay flagged

  • Progress step 132

    Issued 1 Jun 2026 · €4,670,108 · delay flagged

  • Progress step 133

    Issued 1 Jul 2026 · €4,725,856 · delay flagged

  • Progress step 134

    Issued 3 Aug 2026 · €4,781,603 · delay flagged

Similar tenders in the same area

Loading comparison…

Market peer context
Market context from ANAC open data — not a full DIGIWHIST calibration.

Single bidder — In sector Culture, sport and recreation in Aosta Valley, 0.4% of comparable tenders drew at least 3 bidders (of 461 tenders). The score alone does not say whether that is unusual; this context does.

0.4% of comparable tenders had ≥3 bidders (n=461)

UIF-aligned indicator (experimental)
Open-data risk indicator — for further review. Not a UIF/Bank of Italy endorsement.
Sector comparison

Loading…

Amount vs category

Loading…

Discount vs similar tenders

Loading…

Citizen verifier notes
Share what you verified on official sources — not a verdict
How the score is built
Ruleset 3.3.1 · 21 Sept 2026
Source data & verification

ANAC BDNCP — dati tabellari

Verify on ANAC

Ingested: 20 Sept 2026

Release: 20260801-cig_csv.csv

Days to submit bids: 34

CONCESSIONE PER LA GESTIONE DELLE PISCINE DI PROPRIETÀ REGIONALE — AppaltiWatch