AS FO AZIENDA SANITARIA FRIULI OCCIDENTALE
Amount
Award date
Bids
Published
Estimated tender value
Applicable legal ceiling
National maximum for this procedure type under D.Lgs 36/2023 — verify on official sources.
Award vs estimate
Sector
Loading actions…
Publication / start of procedure
30 Dec 2015
Step completedTime to submit bids
1 Apr 2016
93 days between opening and deadline
Step completedAward
20 Jul 2016
Step completedContract signed
4 Oct 2016
Step completedContract variation
15 Oct 2025
Step completedWork suspension
14 Mar 2020
Step completedWorks progress (SAL)
9 Jun 2026
Loading…
These are automated checks on public data. They help you decide what to look into — they are not criminal findings.
This contract triggered 11 pattern(s) worth a closer look:
Very long deadlines · Variation on record
Friuli-Venezia Giulia · More tenders in this area
AUSA code: 0000400635
PORDENONE
Authority profile| Supplier | Region | Amount | Award date | Status |
|---|---|---|---|---|
| C.M.B. SOCIETA' COOPERATIVA MURATORI E BRACCIANTI DI CARPI ABBREVIABILE IN C.M.B. SOCIETA' COOPERATIVA | — | €109,462,062 | 20 Jul 2016 | AGGIUDICATA |
| IMPRESA POLESE S.R.L. | — | €109,462,062 | 20 Jul 2016 | AGGIUDICATA |
Variations
CAUSE IMPREVISTI E IMPREVEDIBILI ACCERTATE NEI MODI STABILITI DAL REGOLAMENTO
Approved on 15 Oct 2025 · 99
CAUSE IMPREVISTE E IMPREVEDIBILI ACCERTATE NEI MODI STABILITI DAL REGOLAMENTO
Approved on 30 Apr 2025 · 99
SOPRAVVENUTE DISPOSIZIONI LEGISLATIVE E REGOLAMENTARI; EVENTI INERENTI ALLA NATURA E ALLA SPECIFICITÀ DEI BENI SUI QUALI SI INTERVIENE VERIFICATISI IN CORSO D''OPERA
Approved on 22 Oct 2024 · 99
SOPRAVVENUTE DISPOSIZIONI LEGISLATIVE E REGOLAMENTARI; EVENTI INERENTI ALLA NATURA E ALLA SPECIFICITÀ DEI BENI SUI QUALI SI INTERVIENE VERIFICATISI IN CORSO D''OPERA; MIGLIORAMENTO DELL''OPERA E DELLA SUA FUNZIONALITÀ; LAVORI COMPLEMENTARI AI SENSI DELL''ART. 57, C5, L.A.
Approved on 29 Dec 2023 · 99
RINVENIMENTI IMPREVISTI E NON PREVEDIBILI E MIGLIORAMENTO DELL''OPERA E SUA FUNZIONALITÀ
Approved on 9 Dec 2020 · 99
ART.132 C.1 LETT. C) D.LGS.163/2006
Approved on 26 Feb 2019 · 3
LAVORI OPZIONALI PREVISTI NEL BANDO DI GARA. ARTICOLO 57 COMMA 5 LETTERA A.
Approved on 10 Jul 2018 · 99
ART.132 C.1 LETT. A) D.LGS.163/2006
Approved on 12 Jun 2018 · 1
ART.132 C.1 LETT. C) D.LGS.163/2006
Approved on 30 Oct 2017 · 3
Suspensions
PUBBLICO INTERESSE O NECESSITA'
From 14 Mar 2020 · resumed on 4 May 2020
PUBBLICO INTERESSE O NECESSITA'
From 14 Mar 2020 · resumed on 4 May 2020
PUBBLICO INTERESSE O NECESSITA'
From 14 Mar 2020 · resumed on 4 May 2020
PUBBLICO INTERESSE O NECESSITA'
From 14 Mar 2020 · resumed on 4 May 2020
PUBBLICO INTERESSE O NECESSITA'
From 14 Mar 2020 · resumed on 4 May 2020
STATO DI AVANZAMENTO N. 1 \\R\\N(CERTIFICATI DI PAGAMENTO N. 1 E 2)
Issued 26 Jul 2017 · €1,874,563 · payment certified 31 Jul 2017 · delay flagged
STATO DI AVANZAMENTO N. 2\\R\\N(CERTIFICATO DI PAGAMENTO N. 3)
Issued 30 Sept 2017 · €4,756,069 · payment certified 4 Oct 2017 · delay flagged
STATO DI AVANZAMENTO N. 3\\R\\N(CERTIFICATO DI PAGAMENTO N. 4)
Issued 30 Nov 2017 · €8,057,833 · payment certified 6 Dec 2017 · delay flagged
STATO DI AVANZAMENTO N. 4\\R\\N(CERTIFICATO DI PAGAMENTO N. 5)
Issued 31 Jan 2018 · €8,644,083 · payment certified 20 Feb 2018 · delay flagged
STATO DI AVANZAMENTO N. 5\\R\\N(CERTIFICATO DI PAGAMENTO N. 6)
Issued 15 Jun 2018 · €9,050,852 · payment certified 20 Jun 2018 · delay flagged
Progress step 6
Issued 15 Sept 2018 · €11,660,170 · payment certified 9 Oct 2018 · delay flagged
Progress step 7
Issued 15 Nov 2018 · €14,720,028 · payment certified 16 Nov 2018 · delay flagged
Progress step 8
Issued 28 Feb 2019 · €21,059,040 · payment certified 5 Mar 2019 · delay flagged
Progress step 9
Issued 30 Apr 2019 · €25,359,952 · delay flagged
Progress step 10
Issued 30 Jun 2019 · €32,125,290 · payment certified 1 Jul 2019 · delay flagged
Progress step 11
Issued 31 Aug 2019 · €36,916,267 · payment certified 13 Sept 2019 · delay flagged
Progress step 12
Issued 31 Oct 2019 · €40,734,609 · payment certified 13 Nov 2019 · delay flagged
Progress step 13
Issued 31 Dec 2019 · €44,102,173 · payment certified 29 Jan 2020 · delay flagged
Progress step 14
Issued 29 Feb 2020 · €48,359,715 · payment certified 19 Mar 2020 · delay flagged
15° SAL
Issued 31 May 2020 · €52,482,236 · payment certified 1 Jul 2020 · delay flagged
16° SAL
Issued 30 Jun 2020 · €55,809,514 · payment certified 29 Jul 2020 · delay flagged
SAL N. 17 A TUTTO IL 31.08.2020
Issued 31 Aug 2020 · €60,469,678 · payment certified 28 Sept 2020 · delay flagged
18 SAL A TUTTO IL 31.10.2020
Issued 31 Oct 2020 · €66,110,991 · payment certified 19 Nov 2020 · delay flagged
19^ SAL
Issued 31 Dec 2020 · €73,512,950 · payment certified 21 Jan 2021 · delay flagged
SAL A TUTTO IL 28.02.2021
Issued 22 Mar 2021 · €78,023,997 · payment certified 2 Apr 2021 · delay flagged
SAL A TUTTO IL 30.04.2021
Issued 7 May 2021 · €80,651,793 · payment certified 12 May 2021 · delay flagged
SAL 22
Issued 30 Jun 2021 · €81,397,200 · delay flagged
23 SAL
Issued 31 Aug 2021 · €82,310,670 · delay flagged
STATO AVANZAMENTO N. 24 PER LAVORI ESEGUITI A TUTTO IL 31.10.2021
Issued 31 Oct 2021 · €83,702,077 · payment certified 7 Dec 2021 · delay flagged
25° SAL A TUTTO IL 31.12.2021
Issued 28 Jan 2022 · €84,876,052 · payment certified 8 Feb 2022 · delay flagged
26° SAL A TUTTO IL 28.02.2022
Issued 6 Apr 2022 · €86,111,686 · payment certified 13 Apr 2022 · delay flagged
Progress step 27
Issued 11 May 2022 · €90,002,414 · payment certified 18 May 2022 · delay flagged
Progress step 28
Issued 15 Jul 2022 · €92,606,068 · payment certified 19 Jul 2022 · delay flagged
Progress step 29
Issued 15 Sept 2022 · €95,180,905 · payment certified 21 Sept 2022 · delay flagged
Progress step 30
Issued 4 Nov 2022 · €100,849,402 · payment certified 9 Nov 2022 · delay flagged
Progress step 31
Issued 18 Jan 2023 · €107,907,337 · payment certified 25 Jan 2023 · delay flagged
Progress step 32
Issued 17 Mar 2023 · €110,683,215 · payment certified 22 Mar 2023 · delay flagged
Progress step 33
Issued 12 May 2023 · €113,184,018 · payment certified 17 May 2023 · delay flagged
Progress step 34
Issued 30 Jun 2023 · €116,468,745 · payment certified 4 Jul 2023 · delay flagged
Progress step 35
Issued 18 Sept 2023 · €121,647,105 · payment certified 22 Sept 2023 · delay flagged
Progress step 36
Issued 28 Nov 2023 · €124,807,575 · payment certified 30 Nov 2023 · delay flagged
Progress step 37
Issued 23 Jan 2024 · €128,457,613 · payment certified 30 Jan 2024 · delay flagged
Progress step 38
Issued 28 Mar 2024 · €133,112,254 · payment certified 15 Apr 2024 · delay flagged
Progress step 39
Issued 23 May 2024 · €136,634,703 · payment certified 30 May 2024 · delay flagged
Progress step 40
Issued 17 Jul 2024 · €138,922,376 · payment certified 6 Aug 2024 · delay flagged
REALIZZAZIONE DELLA CITTADELLA DELLA SALUTE E DEL NUOVO OSPEDALE DI PORDENONE
Issued 8 Nov 2024 · €141,571,301 · payment certified 14 Nov 2024 · delay flagged
REALIZZAZIONE DELLA CITTADELLA DELLA SALUTE E DEL NUOVO OSPEDALE DI PORDENONE
Issued 23 Jan 2025 · €141,909,784 · payment certified 30 Jan 2025 · delay flagged
REALIZZAZIONE DELLA CITTADELLA DELLA SALUTE E DEL NUOVO OSPEDALE DI PORDENONE
Issued 12 May 2025 · €142,672,189 · payment certified 16 May 2025 · delay flagged
REALIZZAZIONE DELLA CITTADELLA DELLA SALUTE E DEL NUOVO OSPEDALE DI PORDENONE
Issued 15 Dec 2025 · €143,464,063 · payment certified 18 Dec 2025 · delay flagged
REALIZZAZIONE DEL NUOVO OSPEDALE E DELLA CITTADELLA DELLA SALUTE DI PORDENONE
Issued 9 Jun 2026 · €144,923,063 · payment certified 18 Jun 2026 · delay flagged
Loading comparison…
In sector Construction works in Friuli-Venezia Giulia, 12.6% of comparable tenders drew at least 3 bidders (of 13550 tenders).
12.6% of comparable tenders had ≥3 bidders (n=13550)
Loading…
Loading…
Loading…
ANAC BDNCP — dati tabellari
Verify on ANACIngested: 20 Sept 2026
Release: 20260801-cig_csv.csv
Days to submit bids: 93