REALIZZAZIONE NUOVA RESIDENZA UNIVERSITARIA EINSTEIN, VIA EINSTEIN - MILANO
POLITECNICO DI MILANO
Amount
Award date
Bids
Published
Estimated tender value
Applicable legal ceiling
National maximum for this procedure type under D.Lgs 36/2023 — verify on official sources.
Award vs estimate
Sector
Loading actions…
Publication / start of procedure
29 Dec 2015
Step completedTime to submit bids
24 Feb 2016
57 days between opening and deadline
Step completedAward
13 May 2016
Step completedContract signed
16 Jun 2016
Step completedContract variation
31 Oct 2018
Step completedWorks progress (SAL)
1 Feb 2021
Loading…
These are automated checks on public data. They help you decide what to look into — they are not criminal findings.
This contract triggered 6 pattern(s) worth a closer look:
Low competition · Negotiated without call
- Tender with a single bidder What does this mean?
- Negotiated without call What does this mean?
- Repeated awards to the same supplier (same CA, 12 months) What does this mean?
- Works delayed (SAL) What does this mean?
- No start recorded
- Funding source not reported
Lombardy · More tenders in this area
AUSA code: 0000244270
MILANO
Authority profile| Supplier | Region | Amount | Award date | Status |
|---|---|---|---|---|
| ENGIE SERVIZI S.P.A. | — | €13,166,000 | 13 May 2016 | AGGIUDICATA |
| CONSORZIO FRA COOPERATIVE DI PRODUZIONE E LAVORO - CONS.COOP.- S OCIETA' COOPERATIVA IN SIGLA CONSCOOP | — | €13,166,000 | 13 May 2016 | AGGIUDICATA |
| Organisation | Role | Outcome |
|---|---|---|
| CONSORZIO FRA COOPERATIVE DI PRODUZIONE E LAVORO - CONS.COOP.- S OCIETA' COOPERATIVA IN SIGLA CONSCOOP 00140990409 | MANDATARIA | Awarded |
| ENGIE SERVIZI S.P.A. 07149930583 | MANDANTE | Awarded |
Variations
ATTO INTEGRATIVO ? 480.000 DI CUI ? 14.000 ONERI SICUREZZA
Approved on 31 Oct 2018 · 99
SAL 1 SERVIZI FASE 1
Issued 31 May 2017 · €37,363 · payment certified 31 May 2017 · delay flagged
SAL 1 LAVORI FASE 1
Issued 26 May 2017 · €81,196 · payment certified 26 May 2017 · delay flagged
SAL 1 FASE 2 SERVIZI
Issued 16 Jun 2016 · €17,063 · payment certified 16 Jun 2017 · delay flagged
SAL 2 FASE 2 SERVIZI
Issued 4 Aug 2017 · €9,766 · payment certified 4 Aug 2017 · delay flagged
SAL 3 FASE 2 SERVIZI
Issued 24 Oct 2017 · €10,665 · payment certified 24 Oct 2017 · delay flagged
SAL 4 FASE 2 SERVIZI
Issued 22 Nov 2017 · €6,485 · payment certified 22 Nov 2017 · delay flagged
SAL 5 FASE 2 SERVIZI
Issued 29 Dec 2017 · €11,869 · payment certified 29 Dec 2017 · delay flagged
SAL 6 FASE 2 SERVIZI
Issued 16 Feb 2018 · €8,946 · payment certified 16 Feb 2018 · delay flagged
SAL 7 FASE 2 SERVIZI
Issued 23 Mar 2018 · €17,070 · payment certified 23 Mar 2018 · delay flagged
SAL 8 FASE 2 SERVIZI
Issued 27 Apr 2018 · €8,672 · payment certified 27 Apr 2018 · delay flagged
SAL 1 FASE 2 LAVORI
Issued 16 Jun 2017 · €617,619 · payment certified 16 Jun 2017 · delay flagged
SAL 2 LAVORI FASE 2
Issued 4 Aug 2017 · €279,568 · payment certified 4 Aug 2017 · delay flagged
SAL 3 FASE 2 LAVORI
Issued 24 Oct 2017 · €331,988 · payment certified 24 Oct 2017 · delay flagged
SAL 4 FASE 2 LAVORI
Issued 22 Nov 2017 · €352,554 · payment certified 22 Nov 2017 · delay flagged
SAL 5 FASE 2 LAVORI
Issued 29 Dec 2017 · €630,855 · payment certified 29 Dec 2017 · delay flagged
SAL 6 FASE 2 LAVORI
Issued 16 Feb 2018 · €403,591 · payment certified 16 Feb 2018 · delay flagged
SAL 7 FASE 2 LAVORI
Issued 23 Mar 2018 · €400,182 · payment certified 23 Mar 2018 · delay flagged
SAL 8 FASE 2 LAVORI
Issued 27 Apr 2018 · €381,869 · payment certified 27 Apr 2018 · delay flagged
SAL 9 FASE 2 LAVORI
Issued 26 Jun 2018 · €948,664 · payment certified 27 Jun 2018 · delay flagged
SAL 10 FASE 2 LAVORI
Issued 23 Jul 2018 · €763,067 · payment certified 23 Jul 2018 · delay flagged
SAL 11 FASE 2 LAVORI
Issued 14 Sept 2018 · €1,555,203 · payment certified 14 Sept 2018 · delay flagged
SAL 12 FASE 2 LAVORI
Issued 12 Dec 2018 · €1,400,598 · payment certified 12 Dec 2018 · delay flagged
SAL 13 FASE 2 LAVORI
Issued 14 Mar 2019 · €587,509 · payment certified 14 Mar 2019 · delay flagged
SAL 14 FASE 2 LAVORI
Issued 9 Aug 2019 · €225,288 · payment certified 9 Aug 2019 · delay flagged
SAL 15 FASE 2 LAVORI
Issued 30 Apr 2020 · €220,920 · payment certified 30 Apr 2020 · delay flagged
SAL 1C ALLESTIMENTI
Issued 9 Aug 2020 · €189,050 · delay flagged
SAL 2C ALLESTIMENTI
Issued 1 Jun 2021 · €59,700 · delay flagged
SAL 9A SERVIZI
Issued 29 Jun 2018 · €25,098 · delay flagged
SAL 10A SERVIZI
Issued 23 Jul 2018 · €21,561 · delay flagged
SAL 11A SERVIZI
Issued 14 Sept 2018 · €25,007 · delay flagged
SAL 12A SERVIZI
Issued 12 Dec 2018 · €31,968 · delay flagged
SAL 13A SERVIZI
Issued 14 Mar 2019 · €15,925 · delay flagged
SAL 14A SERVIZI
Issued 9 Aug 2019 · €3,074 · delay flagged
SAL 15A SERVIZI
Issued 10 Jun 2021 · €2,583 · delay flagged
SAL 16B LAVORI
Issued 10 Jun 2021 · €827,659 · delay flagged
SAL 1 PT
Issued 1 Jul 2017 · €19,500 · delay flagged
SAL 2 PT
Issued 22 Nov 2017 · €4,500 · delay flagged
SAL 3 PT
Issued 29 Jan 2018 · €5,000 · delay flagged
SAL 4 PT
Issued 10 Apr 2018 · €4,500 · delay flagged
SAL 5 PT
Issued 23 Jul 2018 · €2,100 · delay flagged
SAL 6 PT
Issued 19 Nov 2018 · €6,500 · delay flagged
SAL 7 PT
Issued 1 Feb 2021 · €15,500 · delay flagged
Loading comparison…
Single bidder — In sector Construction works in Lombardy, 10.7% of comparable tenders drew at least 3 bidders (of 49549 tenders). The score alone does not say whether that is unusual; this context does.
10.7% of comparable tenders had ≥3 bidders (n=49549)
Loading…
Loading…
Loading…