COSTRUZIONE LABORATORI PER INNOVAZIONE SVILUPPO E RICERCA POLO MECCATRONICA DI RORERETO - PROGETTAZIONE ED ESECUZIONE
PROVINCIA AUTONOMA DI TRENTO
Amount
Award date
Bids
Published
Estimated tender value
Applicable legal ceiling
National maximum for this procedure type under D.Lgs 36/2023 — verify on official sources.
Award vs estimate
Sector
Loading actions…
Publication / start of procedure
8 Feb 2016
Step completedTime to submit bids
21 Jul 2016
164 days between opening and deadline
Step completedAward
31 Jan 2019
Step completedContract signed
17 Nov 2020
Step completedContract variation
11 Sept 2025
Step completedWork suspension
8 Aug 2024
Step completedWorks progress (SAL)
31 Dec 2025
Loading…
These are automated checks on public data. They help you decide what to look into — they are not criminal findings.
This contract triggered 7 pattern(s) worth a closer look:
Very long deadlines · Only one offer admitted
- Unusually long bid submission period (>90 days) — opposite DIGIWHIST literature tail
- Only one offer admitted What does this mean?
- Discount very different from similar tenders What does this mean?
- Works delayed (SAL) What does this mean?
- Long extension What does this mean?
- No start recorded
- Funding source not reported
Trentino-South Tyrol · More tenders in this area
AUSA code: 0000164588
TRENTO
Authority profile| Supplier | Region | Amount | Award date | Status |
|---|---|---|---|---|
| I.T.I. IMPRESA GENERALE S.P.A. | — | €9,284,045 | 31 Jan 2019 | AGGIUDICATA |
| Organisation | Role | Outcome |
|---|---|---|
| I.T.I. IMPRESA GENERALE S.P.A. 01029050364 | Not reported | Awarded |
Variations
-
Approved on 11 Sept 2025 · 99
-
Approved on 28 Apr 2025 · 99
-
Approved on 19 Jan 2024 · 99
SOPRAVVENUTE ESIGENZE NORMATIVE E REGOLAMENTARI
Approved on 13 Dec 2023 · 7
SOPRAVVENUTE ESIGENZE NORMATIVE E REGOLAMENTARI
Approved on 25 Oct 2022 · 7
Suspensions
REDAZIONE DI VARIANTI IN CORSO DI ESECUZIONE
From 8 Aug 2024
REDAZIONE DI VARIANTI IN CORSO DI ESECUZIONE
From 8 Aug 2024
PAGAMENTO PROGETTAZIONE DEFINITIVA
Issued 17 Nov 2020 · €215,099 · payment certified 17 Nov 2020 · delay flagged
ANTICIPAZIONE PAGAMENTO PROGETTAZIONE ESECUTIVA
Issued 12 Nov 2021 · €94,650 · payment certified 12 Nov 2021 · delay flagged
PAGAMENTO DELLA PROGETTAZIONE ESECUTIVA (MANCA IL 20% DEL CONTRATTO ART.4 PROGETTAZIONE ESECUTIVA) INSERITA LA PENALE PARI A \\U20AC 17'291,91.
Issued 15 Dec 2022 · €321,592 · payment certified 17 Dec 2022 · delay flagged
STATAO AVANZAMENTO N. 1 A TUTTO IL 23/01/2023
Issued 23 Jan 2023 · €61,793 · payment certified 16 Mar 2023 · delay flagged
STATO AVANZAMENTO DEI LAVORI N. 2 A TUTTO IL 15/06/2023
Issued 15 Jun 2023 · €696,945 · payment certified 21 Jun 2023 · delay flagged
STATO AVANZAMENTO DEI LAVORI N.3 A TUTTO IL 16/08/2023
Issued 16 Aug 2023 · €1,291,848 · payment certified 26 Sept 2023 · delay flagged
STATO AVANZAMENTO DEI LAVORI N. 4 A TUTTO IL 31/10/2023
Issued 31 Oct 2023 · €1,729,924 · payment certified 14 Nov 2023 · delay flagged
SAL N.1 - N.4 BIS (RINEGOZIAZIONE CONTRATTO)
Issued 14 Dec 2023 · €930,920 · payment certified 14 Dec 2023 · delay flagged
STATO AVANZAMENTO DEI LAVORI N. 5 A TUTTO IL 31/01/2024
Issued 31 Jan 2024 · €1,721,271 · payment certified 7 Feb 2024 · delay flagged
SAL N.5 BIS (RINEGOZIAZIONE CONTRATTO)
Issued 31 Jan 2024 · €1,097,792 · payment certified 9 Feb 2024 · delay flagged
STATO AVANZAMENTO DEI LAVORI N. 6 A TUTTO IL 01/05/2024
Issued 1 May 2024 · €2,865,063 · payment certified 9 May 2024 · delay flagged
SAL N. 6 BIS (RINEGOZIAZIONE CONTRATTO)
Issued 1 May 2024 · €1,398,670 · payment certified 9 May 2024 · delay flagged
STATO AVANZAMENTO DEO LAVORI N.7 A TUTTO IL 07/07/2024
Issued 1 Jul 2024 · €2,850,738 · payment certified 26 Jul 2024 · delay flagged
SAL N. 7 BIS (RINEGOZIAZIONE CONTRATTO)
Issued 1 Jul 2024 · €1,422,279 · payment certified 26 Jul 2024 · delay flagged
STATO AVANZAMENTO LAVORI N.8
Issued 2 Sept 2024 · €4,377,086 · payment certified 23 Sept 2024 · delay flagged
SAL N.8 BIS
Issued 2 Sept 2024 · €1,429,906 · payment certified 23 Sept 2024 · delay flagged
STATO AVANZAMENTO DEI LAVORI N. 9
Issued 31 Oct 2024 · €4,930,194 · payment certified 22 Nov 2024 · delay flagged
SAL N. 9 BIS
Issued 31 Oct 2024 · €1,431,331 · payment certified 22 Nov 2024 · delay flagged
STATO AVANZAMENTO DEI LAVORI N.10
Issued 31 Dec 2024 · €5,635,447 · payment certified 17 Jan 2025 · delay flagged
SAL N. 10 BIS
Issued 31 Dec 2024 · €1,450,059 · payment certified 29 Jan 2025 · delay flagged
STATO AVANZAMENTO DEI LAVORI N.11
Issued 28 Feb 2025 · €6,625,537 · payment certified 14 Mar 2025 · delay flagged
SAL N. 11 BIS
Issued 28 Feb 2025 · €1,452,565 · payment certified 14 Mar 2025 · delay flagged
SAL N. 12 BIS
Issued 29 Apr 2025 · €3,204,260 · payment certified 29 Apr 2025 · delay flagged
STATO AVANZAMENTO DEI LAVORI N. 12
Issued 30 Apr 2025 · €7,618,599 · payment certified 26 May 2025 · delay flagged
SAL N. 14
Issued 1 Sept 2025 · €8,947,207 · payment certified 15 Sept 2025 · delay flagged
SAL N.13 BIS
Issued 30 Jun 2025 · €3,208,315 · payment certified 31 Jul 2025 · delay flagged
SAL N. 14 BIS
Issued 1 Sept 2025 · €4,784,165 · payment certified 19 Sept 2025 · delay flagged
SAL N. 13
Issued 30 Jun 2025 · €8,244,658 · payment certified 17 Jul 2025 · delay flagged
SAL N.13 BIS
Issued 30 Jun 2025 · €3,208,315 · payment certified 31 Jul 2025 · delay flagged
SAL N.15
Issued 31 Oct 2025 · €9,566,403 · payment certified 28 Nov 2025 · delay flagged
SAL N. 15 BIS
Issued 31 Oct 2025 · €5,399,286 · payment certified 28 Nov 2025 · delay flagged
SAL N. 16
Issued 31 Dec 2025 · €9,874,648 · payment certified 6 Feb 2026 · delay flagged
SAL N.16 BIS
Issued 31 Dec 2025 · €5,422,626 · payment certified 11 Feb 2026 · delay flagged
Loading comparison…
In sector Construction works in Trentino-South Tyrol, 9.9% of comparable tenders drew at least 3 bidders (of 23630 tenders).
9.9% of comparable tenders had ≥3 bidders (n=23630)
Loading…
Loading…
Loading…
Source data & verification
ANAC BDNCP — dati tabellari
Verify on ANACIngested: 5 Aug 2026
Release: 20260401-cig_csv.csv
Days to submit bids: 164