REALIZZAZIONE NUOVO OSPEDALE DI SAN GAVINO MONREALE
AZIENDA UNITA' SANITARIA LOCALE N. 6 SANLURI
Amount
Award date
Bids
Published
Estimated tender value
Applicable legal ceiling
National maximum for this procedure type under D.Lgs 36/2023 — verify on official sources.
Award vs estimate
Sector
Loading actions…
Publication / start of procedure
31 Jul 2015
Step completedTime to submit bids
27 Oct 2015
88 days between opening and deadline
Step completedAward
18 Jan 2016
Step completedContract signed
28 Jan 2020
Step completedContract variation
23 Dec 2021
Step completedWork suspension
28 Oct 2024
Step completedWorks progress (SAL)
28 Feb 2026
Loading…
These are automated checks on public data. They help you decide what to look into — they are not criminal findings.
This contract triggered 8 pattern(s) worth a closer look:
Variation on record · Multiple variations
- Contract variation recorded on ANAC What does this mean?
- Multiple variations on the same contract What does this mean?
- Work suspension recorded What does this mean?
- Works delayed (SAL) What does this mean?
- Long extension What does this mean?
- Final cost well above award
- No closure recorded
- Significant subcontracting
| Supplier | Region | Amount | Award date | Status |
|---|---|---|---|---|
| INSO SISTEMI PER LE INFRASTRUTTURE SOCIALI S.P.A IN FORMA ABBREVIATA INSO S.P.A. | — | €40,691,242 | 18 Jan 2016 | AGGIUDICATA |
| Organisation | Role | Outcome |
|---|---|---|
| INSO SISTEMI PER LE INFRASTRUTTURE SOCIALI S.P.A IN FORMA ABBREVIATA INSO S.P.A. 01226390480 | Not reported | Awarded |
Variations
ADEGUAMENTO PROGETTO ESECUTIVO A SOPPRAVENUTE NORMATIVE
Approved on 23 Dec 2021 · 99
ADEGUAMENTO PROGETTO ESECUTIVO A SOPPRAVENUTE NORMATIVE
Approved on 23 Dec 2021 · 99
Suspensions
AVVERSE CONDIZIONI CLIMATICHE
From 28 Oct 2024 · resumed on 3 Dec 2024
AVVERSE CONDIZIONI CLIMATICHE
From 28 Oct 2024 · resumed on 3 Dec 2024
STATO DI AVANZAMENTO N. 1 AL 31/12/2022
Issued 7 Jul 2023 · €613,600 · payment certified 27 Jul 2023 · delay flagged
STATO DI AVANZAMENTO LAVORI N. 2 AL 28/02/2023
Issued 7 Jul 2023 · €307,000 · payment certified 27 Jul 2023 · delay flagged
STATO DI AVANZAMENTO LAVORI N. 3 AL 30/04/2023
Issued 7 Jul 2023 · €465,000 · payment certified 27 Jul 2023 · delay flagged
STATO DI AVANZAMENTO LAVORI N. 4 AL 30/06/2023
Issued 11 Sept 2023 · €1,312,100 · payment certified 10 Oct 2023 · delay flagged
STATO DI AVANZAMENTO N. 5 A TUTTO IL 31/08/2023
Issued 31 Aug 2023 · €977,400 · payment certified 23 Feb 2024 · delay flagged
STATO AVANZAMENTO LAVORI N. 6 A TUTTO IL 31/10/2023
Issued 31 Oct 2023 · €912,300 · payment certified 31 Oct 2023 · delay flagged
STATO DI AVANZAMENTO LAVORI N.7 A TUTTO IL 31/12/2023
Issued 31 Dec 2023 · €770,100 · payment certified 31 Dec 2023 · delay flagged
STATO DI AVANZAMENTO LAVORI N.8 A TUTTO IL 28/12/2024
Issued 28 Dec 2024 · €831,900 · payment certified 28 Dec 2024 · delay flagged
STATO DI AVANZAMENTO LAVORI N.9 A TUTTO IL 30/04/2024
Issued 30 Apr 2024 · €1,201,100 · payment certified 30 Apr 2024 · delay flagged
STATO DI AVANZAMENTO LAVORI N.10 A TUTTO IL 30/06/2024
Issued 30 Jun 2024 · €1,481,000 · payment certified 30 Jun 2024 · delay flagged
STATO DI AVANZAMENTO LAVORI N. 11 A TUTTO IL 31/08/2024
Issued 31 Aug 2024 · €927,500 · payment certified 31 Aug 2024 · delay flagged
STATO DI AVANZAMENTO LAVORI N.12 A TUTTO IL 31/10/2024
Issued 31 Oct 2024 · €1,690,400 · payment certified 31 Oct 2024 · delay flagged
STATO DI AVANZAMENTO LAVORI N.13 A TUTTO IL 31/12/2024
Issued 31 Dec 2024 · €486,800 · payment certified 31 Dec 2024 · delay flagged
STATO DI AVANZAMENTO LAVORI N. 14 A TUTTO IL 28/02/2025
Issued 28 Feb 2025 · €1,527,300 · payment certified 28 Feb 2025 · delay flagged
STATO DI AVANZAMENTO N.15 A TUTTO IL 30.04.2025
Issued 30 Apr 2025 · €2,882,700 · payment certified 30 Apr 2025 · delay flagged
STATO DI AVANZAMENTO LAVORI N. 16 A TUTTO IL 30.06.2025
Issued 30 Jun 2025 · €500,900 · payment certified 30 Jun 2025 · delay flagged
STATO DI AVANZAMENTO LAVORI N.17A TUTTO IL 31.08.2025
Issued 31 Aug 2025 · €1,344,800 · payment certified 31 Aug 2025 · delay flagged
STATO DI AVANZAMENTO LAVORI N. 18 A TUTTO IL 31.10.2025
Issued 31 Oct 2025 · €934,900 · payment certified 31 Oct 2025 · delay flagged
STATO DI AVANZAMENTO LAVORI N. 19 A TUTTO IL 31.12.2025
Issued 31 Dec 2025 · €661,600 · payment certified 31 Dec 2025 · delay flagged
STATO DI AVANZAMENTO LAVORI N.20 A TUTTO IL 28.02.2026
Issued 28 Feb 2026 · €560,400 · payment certified 28 Feb 2026 · delay flagged
Loading comparison…
In sector Construction works, 11.5% of comparable tenders drew at least 3 bidders (of 414197 tenders).
11.5% of comparable tenders had ≥3 bidders (n=414197)
Loading…
Loading…
Loading…
Source data & verification
ANAC BDNCP — dati tabellari
Verify on ANACIngested: 20 Sept 2026
Release: 20260801-cig_csv.csv
Days to submit bids: 88