OPK679-679B - LAVORI DI RISANAMENTO DI PALAZZO LUTTI -SALVADORI DA ADIBIRE A POLO CULTURALE INCENTRATO SULLA BIBLIOTECA CIVICA - 5^ E 6^ LOTTO
COMUNE DI RIVA DEL GARDA
Amount
Award date
Bids
Published
Estimated tender value
Applicable legal ceiling
National maximum for this procedure type under D.Lgs 36/2023 — verify on official sources.
Award vs estimate
Sector
Loading actions…
Publication / start of procedure
7 Jul 2015
Step completedTime to submit bids
16 Sept 2015
69 days between opening and deadline
Step completedAward
27 Jun 2016
Step completedContract signed
1 Mar 2017
Step completedContract variation
19 Jun 2019
Step completedWork suspension
3 Aug 2018
Step completedWorks progress (SAL)
17 Apr 2020
Loading…
These are automated checks on public data. They help you decide what to look into — they are not criminal findings.
This contract triggered 7 pattern(s) worth a closer look:
Variation on record · Multiple variations
- Contract variation recorded on ANAC What does this mean?
- Multiple variations on the same contract What does this mean?
- Work suspension recorded What does this mean?
- Discount very different from similar tenders What does this mean?
- Works delayed (SAL) What does this mean?
- Final cost well above award
- Significant subcontracting
Trentino-South Tyrol · More tenders in this area
AUSA code: 0000241873
RIVA DEL GARDA
Authority profile| Supplier | Region | Amount | Award date | Status |
|---|---|---|---|---|
| SELI MANUTENZIONI GENERALI S.R.L. | — | €1,290,028 | 27 Jun 2016 | AGGIUDICATA |
| Organisation | Role | Outcome |
|---|---|---|
| SELI MANUTENZIONI GENERALI S.R.L. 07610090156 | Not reported | Awarded |
Variations
MODIFICHE ALLE PREVISIONI PROGETTUALI PER GARANTIRE UNA MIGLIORE FUNZIONALITÀ DELL''INFRASTRUTTURA
Approved on 19 Jun 2019 · 99
MODIFICHE PREVISIONI PROGETTUALI PER MIGLIORAMENTO DELLA FUNZIONALITÀ DELL''INFRASTRUTTURA
Approved on 19 Jun 2019 · 99
Suspensions
REDAZIONE DI VARIANTI IN CORSO DI ESECUZIONE
From 3 Aug 2018 · resumed on 14 Aug 2019
REDAZIONE DI VARIANTI IN CORSO DI ESECUZIONE
From 3 Aug 2018 · resumed on 14 Aug 2019
Progress step 1
Issued 9 Mar 2018 · €42,977 · payment certified 30 May 2018 · delay flagged
Progress step 2
Issued 9 Mar 2018 · €51,057 · payment certified 30 May 2018 · delay flagged
Progress step 3
Issued 29 May 2018 · €92,463 · payment certified 26 Jun 2018 · delay flagged
Progress step 4
Issued 26 Jul 2018 · €137,204 · payment certified 17 Aug 2018 · delay flagged
Progress step 5
Issued 29 May 2018 · €82,499 · delay flagged
Progress step 6
Issued 26 Jul 2018 · €141,606 · delay flagged
Progress step 7
Issued 4 Dec 2019 · €164,966 · payment certified 18 Dec 2019 · delay flagged
Progress step 8
Issued 4 Dec 2019 · €250,853 · payment certified 18 Dec 2019 · delay flagged
Progress step 9
Issued 17 Apr 2020 · €486,741 · payment certified 17 Apr 2020 · delay flagged
Loading comparison…
In sector Construction works in Trentino-South Tyrol, 10.4% of comparable tenders drew at least 3 bidders (of 24431 tenders).
10.4% of comparable tenders had ≥3 bidders (n=24431)
Loading…
Loading…
Loading…
Source data & verification
ANAC BDNCP — dati tabellari
Verify on ANACIngested: 20 Sept 2026
Release: 20260801-cig_csv.csv
Days to submit bids: 69