ASL LATINA
Amount
Award date
Bids
Published
Estimated tender value
Applicable legal ceiling
National maximum for this procedure type under D.Lgs 36/2023 — verify on official sources.
Award vs estimate
Sector
Loading actions…
Publication / start of procedure
16 Jan 2015
Step completedTime to submit bids
25 Mar 2015
68 days between opening and deadline
Step completedAward
18 Sept 2015
Step completedContract signed
20 Nov 2015
Step completedContract variation
23 Nov 2020
Step completedWorks progress (SAL)
21 Oct 2021
Loading…
These are automated checks on public data. They help you decide what to look into — they are not criminal findings.
This contract triggered 7 pattern(s) worth a closer look:
Variation on record · Multiple variations
| Supplier | Region | Amount | Award date | Status |
|---|---|---|---|---|
| FURLAN COSTRUZIONI ITALIA S.R.L. | — | €4,062,610 | 18 Sept 2015 | AGGIUDICATA |
| MARINELLI ARNALDO SOCIETA' A RESPONSABILITA' LIMITATA IN FORMA ABBREVIATA MARINELLI ARNALDO S.R.L. | — | €4,062,610 | 18 Sept 2015 | AGGIUDICATA |
| Organisation | Role | Outcome |
|---|---|---|
| C.N. COSTRUZIONI GENERALI S.P.A. 05931780729 | MONOSOGGETTIVO | Participant |
| CNS CONSORZIO NAZIONALE SERVIZI SOCIETA' COOPERATIVA 02884150588 | MONOSOGGETTIVO | Participant |
| FURLAN COSTRUZIONI ITALIA S.R.L. 02628510592 | MANDATARIA | Awarded |
| MARINELLI ARNALDO SOCIETA' A RESPONSABILITA' LIMITATA IN FORMA ABBREVIATA MARINELLI ARNALDO S.R.L. 02334770597 | MANDANTE | Awarded |
| MUGNAI - SOCIETA' PER AZIONI 00427590583 | MONOSOGGETTIVO | Participant |
| NATUNA S.R.L. - SOCIETA' BENEFIT 13075200157 | MONOSOGGETTIVO | Participant |
| REKEEP S.P.A. 02402671206 | MONOSOGGETTIVO | Participant |
| ROMEO GESTIONI S.P.A. 05850080630 | MONOSOGGETTIVO | Participant |
Variations
DELIBERAZIONE N. 1341 DEL 23.11.2020 - PROROGA TECNICA ATI FURLAN COSTRUZIONI ITALIA SRL/MARINELLI ARNALDO SRL DAL 01.10.2020 AL 31.03.2021
Approved on 23 Nov 2020 · 99
DELIBERAZIONE N. 445 DEL 02.04.2020 - PROROGA TECNICA ALL''ATI FURLAN/MARINELLI DAL 01.04.2020 AL 30.09.2020 NELLE MORE DELL''AGGIUDICAZIONE DELLA GARA INDETTA CON DELIBERAZIONE N. 1131 DEL 20.12.2018
Approved on 2 Apr 2020 · 99
DELIBERAZIONE N. 72 DEL 22.01.2020- PROROGA TECNICA ALL''ATI FURLAN/MARINELLI DAL 01.01.2020 AL 31.03.2020 NELLE MORE DELL''AGGIUDICAZIONE DELL GARA INDETTA CON DELIBERAZIONE N. 1131 DEL 20.12.2018
Approved on 22 Jan 2020 · 99
DELIBERAZIONE N. 1007 DEL 04.11.2019 - PROROGA TECNICA ALL''ATI FURLAN/MARINELLI DAL 01.10.2019 AL 31.12.2019 NELLE MORE DELL''AGGIUDICAZIONE DELLA GARA INDETTA CON DELIBERAZIONE N. N.1131 DEL 20.12.2018
Approved on 4 Nov 2019 · 99
DELIBERAZIONE N. 762 DEL 02.08.2019 - PROROGA TECNICA ALL''ATI FURLAN/MARINELLI DAL 01.07.2019 AL 30.09.2020 NELLE MORE DELL''ESPLETAMENTO DELLA GARA INDETTA CON DELIBERAZIONE N. N. 1131 DEL 20.12.2018
Approved on 2 Aug 2019 · 99
DELIBERAZIONE N. 06 DEL 9 GENNAIO 2019 - PROROGA TECNICA ALL''ATI FURLAN/MARINELLI DAL 01.01.2019 AL 30.06.2019 NELLE MORE DELL''ESPLETAMENTO DELLA GARA INDETTA CON DELIBERAZIONE N. 1131 DEL 20.12.2018
Approved on 9 Jan 2019 · 99
RINNOVO DEL CONTRATTO PER UNA ANNUALITÀ PREVISTO IN SEDE DI GARA (RICALCOLO DEL Q.E. PER I COMPLESSIVI 3 ANNI)
Approved on 27 Nov 2017 · 99
STATO DI AVANZAMENTO N. 1 A TUTTO IL 31.01.2016
Issued 1 Feb 2016 · €94,692 · payment certified 1 Feb 2016 · delay flagged
STATO AVANZAMENTO LAVORI N. 2 A TUTTO IL 29.02.2016
Issued 29 Feb 2016 · €189,384 · payment certified 29 Feb 2016 · delay flagged
STATO DI AVANZAMANETO LAVORI N. 3 A TUTTO IL 31.03.2016
Issued 31 Mar 2016 · €284,076 · payment certified 31 Mar 2016 · delay flagged
STATO AVANZAMENTO LAVORI N.4 A TUTTO IL 30/04/2016
Issued 2 May 2016 · €378,768 · payment certified 2 May 2016 · delay flagged
STATO AVANZAMENTO LAVORI N.5 A TUTTO IL 31.05.2016
Issued 31 May 2016 · €473,460 · payment certified 31 May 2016 · delay flagged
STATO AVANZAMENTO LAVORI N. 6 A TUTTO IL 30/06/2016
Issued 30 Jun 2016 · €568,152 · payment certified 30 Jun 2016 · delay flagged
STATO AVANZAMENTO LAVORI N.7 (MAUTENZIONE EXTRA CANONE PERIODO GENNAIO/APRILE 2016)
Issued 1 Jul 2016 · €759,219 · payment certified 1 Jul 2016 · delay flagged
STATO AVANZAMENTO LAVORI N. 8 A TUTTO IL 01.07.2016 - RIF. LAVORI TERRAZZO DI COPERTURA - AFFIDAMENTO DELIB. 77/2016 - CONSUNTIVO 219
Issued 12 Jul 2016 · €938,711 · payment certified 12 Jul 2016 · delay flagged
STATO AVANZAMENTO LAVORI N. 9 A TUTTO IL 31.07.2016
Issued 1 Aug 2016 · €1,033,403 · payment certified 1 Aug 2016 · delay flagged
STATO AVANZAMENTO LAVORI N. 10 A TUTTO IL 31.08.2016\\R\\NMANUTENZIONE ORDINARIA
Issued 31 Aug 2016 · €1,128,095 · payment certified 31 Aug 2016 · delay flagged
STATO AVANZAMENTO LAVORI N. 11 A TUTTO IL 22.09.2016 (LAVORI DI RIPRISTINO INTONACO CORNICIONI PRESSO COMUNITÀ MARICAE, MINTURNO)
Issued 22 Sept 2016 · €1,159,352 · payment certified 22 Sept 2016 · delay flagged
STATO AVANZAMENTO LAVORI N. 12 A TUTTO IL 30.09.2016 - CANONE ORDINARIO
Issued 30 Sept 2016 · €1,254,044 · payment certified 30 Sept 2016 · delay flagged
STATO AVANZAMENTO LAVORI N. 13 A TUTTO IL 31.08.2016
Issued 21 Oct 2016 · €1,440,773 · payment certified 21 Oct 2016 · delay flagged
STATO AVANZAMENTO LAVORI A TUTTO IL 31.10.2016 - CANONE ORDINARIO
Issued 31 Oct 2016 · €1,535,465 · payment certified 31 Oct 2016 · delay flagged
STATO AVANZAMENTO LAVORI N. 15 A TUTTO IL 07.11.2016 - RIFERIMENTO LAVORI REPARTO RADIOLOGIA GORETTI
Issued 7 Nov 2016 · €1,661,071 · payment certified 7 Nov 2016 · delay flagged
STATO AVANZAMENTO LAVORI N. 16 A TUTTO IL 30/11/2016
Issued 30 Nov 2016 · €1,755,763 · payment certified 30 Nov 2016 · delay flagged
STATO AVANZAMENTO LAVORI N. 17 A TUTTO IL 31.12.2016
Issued 31 Dec 2016 · €1,850,455 · payment certified 31 Dec 2016 · delay flagged
STATO AVANZAMENTO LAVORI N. 18 A TUTTO IL 31/12/2016 - LAVORI RISTRUTTURAZIONE BLOCCO OPERATORIO DI FORMIA - DEL. 408/CS DEL 21.09.2016
Issued 16 Jan 2017 · €1,927,764 · payment certified 16 Jan 2017 · delay flagged
STATO AVANZAMENTO LAVORI N. 19 A TUTTO IL 31.12.2016
Issued 28 Jan 2017 · €1,948,616 · payment certified 28 Jan 2017 · delay flagged
STATO AVANZAMENTO LAVORI N. 20 A TUTTO IL 31/12/2016
Issued 31 Jan 2017 · €2,164,678 · payment certified 31 Jan 2017 · delay flagged
STATO AVANZAMENTO LAVORI N. 21 A TUTTO IL 31.01.2017 - RIF. CANONE ORDINARIO GENNAIO 2017
Issued 31 Jan 2017 · €2,259,370 · payment certified 31 Jan 2017 · delay flagged
STATO AVANZAMENTO LAVORI N. 22 A TUTTO IL 28/02/2017
Issued 28 Feb 2017 · €2,354,062 · payment certified 28 Feb 2017 · delay flagged
STATO AVANZAMENTO LAVORI N. 23 A TUTTO IL 31/03/2017 - CANONE ORDINARIO MARZO
Issued 31 Mar 2017 · €2,448,754 · payment certified 31 Mar 2017 · delay flagged
STATO AVANZAMENTO LAVORI N. 24 A TUTTO IL 30/04/2017
Issued 2 May 2017 · €2,543,446 · payment certified 2 May 2017 · delay flagged
STATO AVANZAMENTO LAVORI N. 25 A TUTTO IL 30/04/2017
Issued 9 May 2017 · €2,569,665 · payment certified 9 May 2017 · delay flagged
STATO AVANZAMENTO LAVORI N. 26 A TUTTO IL 30/04/2017 - MANUTENZIONE EXTRA CANONE GENNAIO/APRILE 2017
Issued 1 Jun 2017 · €2,835,977 · payment certified 1 Jun 2017 · delay flagged
STATO AVANZAMENTO LAVORI N. 27 A TUTTO IL 31/05/2017 - CANONE ORDINARIO MAGGIO 2017
Issued 1 Jun 2017 · €2,930,669 · payment certified 1 Jun 2017 · delay flagged
STATO AVANZAMENTO LAVORI N. 28 A TUTTO IL 10/05/2017 - INTERVENTO STRAORDINARIO PRESSO IL SERD DI TERRACINA
Issued 6 Jun 2017 · €2,950,897 · payment certified 6 Jun 2017 · delay flagged
STATO AVANZAMENTO LAVORI N. 29 A TUTTO IL 16/06/2017
Issued 28 Jun 2017 · €2,966,836 · payment certified 28 Jun 2017 · delay flagged
STATO AVANZAMENTO LAVORI N. 30 A TUTTO IL 30/06/2017
Issued 3 Jul 2017 · €3,061,528 · payment certified 3 Jul 2017 · delay flagged
STATO AVANZAMENTO LAVORI N. 31 A TUTTO IL 31/07/2017
Issued 31 Jul 2017 · €3,156,220 · payment certified 31 Jul 2017 · delay flagged
STATO DI AVANZAMENTO N. 32 A TUTTO IL 31/08/2017 - CANONE ORDINARIO AGOSTO
Issued 31 Aug 2017 · €3,250,912 · payment certified 31 Aug 2017 · delay flagged
STATO AVANZAMENTO LAVORI N. 33 A TUTTO IL 30.09.2017
Issued 2 Oct 2017 · €3,345,604 · payment certified 2 Oct 2017 · delay flagged
STATO AVANZAMENTO LAVORI N. 34 A TUTTO IL 31.08.2017 - MANUTENZIONE EXTRA CANONE MAGGIO/AGOSTO
Issued 9 Oct 2017 · €3,527,720 · payment certified 9 Oct 2017 · delay flagged
STATO AVANZAMENTO LAVORI N. 35 A TUTTO IL 31.10.2017 - MANUTENZIONE ORDINARIA A CANONE OTTOBRE 2017
Issued 31 Oct 2017 · €3,622,412 · payment certified 31 Oct 2017 · delay flagged
STATO AVANZAMENTO LAVORI N. 36 A TUTTO IL 30.11.2017 - CANONE ORDINARIO
Issued 1 Dec 2017 · €3,717,104 · payment certified 1 Dec 2017 · delay flagged
STATO AVANZAMENTO LAVORI N. 37 A TUTTO IL 31/12/2017
Issued 2 Jan 2018 · €3,811,796 · payment certified 2 Jan 2018 · delay flagged
STATO AVANZAMENTO LAVORI A TUTTO IL 31.12.2017 - MANUTENZIONE EXTRA CANONE SETT/DIC 2017
Issued 2 Feb 2018 · €4,064,053 · payment certified 2 Feb 2018 · delay flagged
STATO AVANZAMENTO LAVORI N. 39 A TUTTO IL 31.01.2018 - RIF. ORDINARIA GEN. 2018
Issued 2 Feb 2018 · €4,158,745 · payment certified 2 Feb 2018 · delay flagged
STATO AVANZAMENTO LAVORI N. 40 A TUTTO IL 28.02.2018 - CANONE ORDINARIO FEBBRAIO 2018
Issued 28 Feb 2018 · €4,253,437 · payment certified 28 Feb 2018 · delay flagged
STATO AVANZAMENTO N. 41 A TUTTO IL 31.03.2018 - ORDINARIO MARZO
Issued 3 Apr 2018 · €4,348,129 · payment certified 3 Apr 2018 · delay flagged
STATO AVANZAMENTO LAVORI N. 42 A TUTTO IL 19.04.2018 - LAVORI PAVIMENTO INGRESSO PRINCIPALE DI FORMIA
Issued 19 Apr 2018 · €4,369,694 · payment certified 19 Apr 2018 · delay flagged
STATO AVANZAMENTO LAVORI N. 43 A TUTTO IL 30.04.2018 - ORDINARIA APRILE
Issued 30 Apr 2018 · €4,464,386 · payment certified 30 Apr 2018 · delay flagged
STATO AVANZAMENTO LAVORI N. 44 A TUTTO IL 31.05.2018 - CANONE MAGGIO
Issued 31 May 2018 · €4,559,008 · payment certified 31 May 2018 · delay flagged
STATO AVANZAMENTO LAVORI A TUTTO IL 30.04.2018 - EXTRA CANONE 2018 GEN/APR
Issued 14 Jun 2018 · €4,761,837 · payment certified 14 Jun 2018 · delay flagged
STATO AVANZAMENTO LAVORI A TUTTO IL 30.06.2018 - CANONE ORDINARIO GIUGNO
Issued 2 Jul 2018 · €4,856,529 · payment certified 2 Jul 2018 · delay flagged
STATO AVANZAMENTO N. 47 LAVORI A TUTTO IL 11/07/2018
Issued 11 Jul 2018 · €4,873,178 · payment certified 11 Jul 2018 · delay flagged
STATO AVANZAMENTO N. 48 LAVORI A TUTTO IL 13/07/2018
Issued 13 Jul 2018 · €4,904,817 · payment certified 13 Jul 2018 · delay flagged
STATO AVANZAMENTO N. 49 LAVORI A TUTTO IL 18/07/2018
Issued 18 Jul 2018 · €4,955,196 · payment certified 18 Jul 2018 · delay flagged
SAL N. 50 A TUTTO IL 31.07.2018
Issued 31 Jul 2018 · €5,049,888 · payment certified 31 Jul 2018 · delay flagged
STATO AVANZAMENTO N. 51 A TUTTO IL 31/08/2018
Issued 1 Sept 2018 · €5,144,580 · payment certified 1 Sept 2018 · delay flagged
STATO AVANZAMENTO LAVORI N. 52 A TUTTO IL 30.09.2018
Issued 1 Oct 2018 · €5,239,272 · payment certified 1 Oct 2018 · delay flagged
STATO AVANZAMENTO LAVORI N. 53 A TUTTO IL 31.08.2018 - 2°EXTRA CANONE MAG/AGO
Issued 11 Oct 2018 · €5,420,778 · payment certified 11 Oct 2018 · delay flagged
STATO AVANZAMENTO LAVORI A TUTTO IL 31.10.2018 - CANONE ORDINARIO OTTOBRE 2018
Issued 2 Nov 2018 · €5,515,470 · payment certified 2 Nov 2018 · delay flagged
STATO AVANZAMENTO LAVORI N. 55 A TUTTO IL 30.11.2018 - CANONE ORDINARIO NOVEMBRE
Issued 3 Dec 2018 · €5,610,162 · payment certified 3 Dec 2018 · delay flagged
STATO AVANZAMENTO LAVORI N. 56 A TUTTO IL 05.12.2018 - EX OMNI SERD PRIVERNO (LT)
Issued 5 Dec 2018 · €5,629,566 · payment certified 5 Dec 2018 · delay flagged
STATO AVANZAMENTO LAVORI N. 57 - CANONE MANUTENZIONE ORDINARIA DICEMBRE 2018
Issued 31 Dec 2018 · €5,724,258 · payment certified 31 Dec 2018 · delay flagged
CERTIFICATO DI PAGAMENTO N. 58 - MANUTENZIONE EXTRA CANONE PERIODO 31.08.2018 - 31.12.2018
Issued 25 Jan 2019 · €5,889,807 · payment certified 25 Jan 2019 · delay flagged
CERTIFICATO DI PAGAMENTO N. 59 DEL 01.02.2019 - CANONE MANUTENZIONE ORDINARIA MESE GENNAIO 2019
Issued 1 Feb 2019 · €5,984,499 · payment certified 1 Feb 2019 · delay flagged
CERTIFICATO DI PAGAMENTO N. 60 DEL 01.03.2019 - CANONE MANUTENZIONE ORDINARIA MESE FEBBRAIO 2019
Issued 1 Mar 2019 · €6,079,191 · payment certified 1 Mar 2019 · delay flagged
STATO AVANZAMENTO LAVORI N. 61 A TUTTO IL 31.03.2019
Issued 1 Apr 2019 · €6,173,883 · payment certified 1 Apr 2019 · delay flagged
STATO AVANZAMENTO LAVORI N. 62 A TUTTO IL 30.04.2019
Issued 2 May 2019 · €6,268,575 · payment certified 2 May 2019 · delay flagged
STATO AVANZAMENTO LAVORI N. 63 A TUTTO IL 31.05.2019
Issued 3 Jun 2019 · €6,363,267 · payment certified 3 Jun 2019 · delay flagged
STATO AVANZAMENTO LAVORI N. 64 A TUTTO IL 30.04.2019 - 1° EXTRA CANONE 2019
Issued 10 Jun 2019 · €6,537,667 · payment certified 10 Jun 2019 · delay flagged
STATO AVANZAMENTO LAVORI N. 65 A TUTTO IL 30.06.2019
Issued 1 Jul 2019 · €6,632,359 · payment certified 1 Jul 2019 · delay flagged
STATO AVANZAMENTO LAVORI N. 66 A TUTTO IL 31.07.2019
Issued 1 Aug 2019 · €6,727,051 · payment certified 1 Aug 2019 · delay flagged
STATO AVANZAMENTO LAVORI N.67 - LAVORI IMPERMEABILIZZAZIONE TERRAZZO PRESSO SERD DI TERRACINA - C
Issued 2 Aug 2019 · €6,739,483 · payment certified 2 Aug 2019 · delay flagged
STATO AVANZAMENTO LAVORI N. 68 PER MANUTENZIONE STRAORDINARIA TERRAZZO COPERTURA B.O. DEL PO LATINA
Issued 5 Aug 2019 · €6,779,274 · payment certified 5 Aug 2019 · delay flagged
STATO AVANZAMENTO LAVORI N. 69 MANUTENZIONE STRAORDINARIA POLIAMBULATORI EX INAM DISTRETTO 2 LATINA
Issued 6 Aug 2019 · €6,793,337 · payment certified 6 Aug 2019 · delay flagged
STATO AVANZAMENTO LAVORI N. 70 - MANUTENZIONE STRAORDINARIA LOCALI REPARTO DIALISI DEL PO LATINA
Issued 7 Aug 2019 · €6,808,525 · payment certified 7 Aug 2019 · delay flagged
STATO AVANZAMENTO LAVORI N. 71 A TUTTO IL 31.08.2019
Issued 2 Sept 2019 · €6,903,217 · payment certified 2 Sept 2019 · delay flagged
STATO AVANZAMENTO LAVORI N. 72 A TUTTO IL 30.09.2020
Issued 1 Oct 2019 · €6,997,909 · payment certified 1 Oct 2019 · delay flagged
STATO AVANZAMENTO LAVORI N. 73 A TUTTO IL 31.10.2019
Issued 4 Nov 2019 · €7,092,601 · payment certified 4 Nov 2019 · delay flagged
STATO AVANZAMENTO LAVORI N. 74 - MANUTENZIONE EXTRA CANONE A TUTTO IL 31.08.2019
Issued 5 Nov 2019 · €7,268,397 · payment certified 5 Nov 2019 · delay flagged
STATO AVANZAMENTO LAVORI N. 75 A TITTO IL 30.11.2019
Issued 2 Dec 2019 · €7,363,089 · payment certified 2 Dec 2019 · delay flagged
STATO AVANZAMENTO LAVORI N. 76 A TUTTO IL 31.12.2019
Issued 2 Jan 2020 · €7,457,781 · payment certified 2 Jan 2020 · delay flagged
STATO AVANZAMENTO LAVORI N. 77 MANUTENZIONE STRAORDINARIA LAVORI DI COPERTURA TERRAZZO PAL.B DEL PO FORMIA
Issued 13 Jan 2020 · €7,505,858 · payment certified 13 Jan 2020 · delay flagged
STATO AVANZAMENTO LAVORI N. 78 A TUTTO IL 31.01.2020
Issued 3 Feb 2020 · €7,600,550 · payment certified 3 Feb 2020 · delay flagged
STATO AVANZAMENTO LAVORI N. 79 - MANUTENZIONE EXTRA CANONE 3/2019 A TUTTO IL 31.12.2019
Issued 17 Feb 2020 · €7,788,920 · payment certified 17 Feb 2020 · delay flagged
STATO AVANZAMENTO LAVORI N. 80 A TUTTO IL 29.02.2020
Issued 2 Mar 2020 · €7,883,612 · payment certified 2 Mar 2020 · delay flagged
STATO AVANZAMENTO N. 81 A TUTTO IL 30.03.2020
Issued 1 Apr 2020 · €7,978,304 · payment certified 1 Apr 2020 · delay flagged
STATO AVANZAMENTO LAVORI N. 82 A TUTTO IL 30.04.2020
Issued 4 May 2020 · €8,072,996 · payment certified 4 May 2020 · delay flagged
STATO AVANZAMENTO LAVORI N. 83 A TUTTO IL 31.05.2020
Issued 3 Jun 2020 · €8,167,688 · payment certified 3 Jun 2020 · delay flagged
STATO AVANZAMENTO LAVORI N. 84 A TUTTO IL 30.06.2020
Issued 1 Jul 2020 · €8,262,380 · payment certified 1 Jul 2020 · delay flagged
STATO AVANZAMENTO N.85 MANUTENZIONE EXTRA CANONE A TUTTO IL 30.04.2020
Issued 2 Jul 2020 · €8,481,652 · payment certified 2 Jul 2020 · delay flagged
STATO AVANZAMENTO N. 86 - MANUTENZIONE STRAORDINARIA RAMPE ACCESSO PS DEL PO FONDI
Issued 3 Jul 2020 · €8,624,507 · payment certified 3 Jul 2020 · delay flagged
INTERVENTI COVID MARZO E APRILE 2020
Issued 15 Jul 2020 · €8,710,901 · payment certified 15 Jul 2020 · delay flagged
INTERVENTI COVID MARZO APRILE 2020
Issued 20 Jul 2020 · €8,769,425 · payment certified 20 Jul 2020 · delay flagged
CANONE MESE DI LUGLIO 2020
Issued 3 Aug 2020 · €8,864,117 · payment certified 3 Aug 2020 · delay flagged
CANONE MESE DI AGOSTO 2020
Issued 7 Sept 2020 · €8,958,809 · payment certified 7 Sept 2020 · delay flagged
LAVORI PUNTO PRELIEVO DI FONDI
Issued 15 Sept 2020 · €8,999,240 · payment certified 15 Sept 2020 · delay flagged
SAL N. 92 MANUTENZIONE ORDINARIA MESE SETTEMBRE 2020
Issued 1 Oct 2020 · €94,219 · payment certified 1 Oct 2020 · delay flagged
SAL N. 93/2020 A TUTTO IL 31 AGOSTO 2020 - INTERVENTI COVID 19
Issued 6 Oct 2020 · €83,402 · payment certified 6 Oct 2020 · delay flagged
SAL N. 94/2020 - 2° EXTRA CANONE
Issued 7 Oct 2020 · €189,378 · payment certified 7 Oct 2020 · delay flagged
SAL N. 95/2020 - DEL.625/2020 - ADEGUAMENTO RETE DISTRIBUZIONE GAS PO GORETTI
Issued 27 Oct 2020 · €58,311 · payment certified 27 Oct 2020 · delay flagged
SAL N. 96/2020 - DEL. 303/2020 LAVORI SU RIVESTIMENTI E PAVIMENTAZIONI SALE OPERATORIE PO TERRACINA
Issued 4 Nov 2020 · €35,150 · payment certified 4 Nov 2020 · delay flagged
SAL N. 97/2020 - DET. 204/2020 CONSUNTIVO LAVORI REALIZZAZIONE GAS MEDICALI PER SALA OPERATORIA PO TERRACINA
Issued 5 Nov 2020 · €38,372 · payment certified 5 Nov 2020 · delay flagged
SAL N. 98/2020 - CANONE OTTOBRE 2020
Issued 26 Nov 2020 · €94,219 · payment certified 26 Nov 2020 · delay flagged
SAL N. 99/2020 CANONE MESE NOVEMBRE 2020
Issued 1 Dec 2020 · €94,219 · payment certified 2 Dec 2020 · delay flagged
SAL N. 100/2020 - DET. 40/2021 - INTERVENTO STRUTTURALE POLIAMBULATORIO SABAUDIA
Issued 17 Dec 2020 · €141,670 · payment certified 17 Dec 2020 · delay flagged
SAL N. 101/2020 - RISTRUTTURAZIONE E ADEGUAMENTO LOCALI PRESSO P.P. MINTURNO
Issued 29 Dec 2020 · €110,009 · payment certified 29 Dec 2020 · delay flagged
SAL N. 102 - CANONE DICEMBRE 2020
Issued 31 Dec 2020 · €94,219 · payment certified 31 Dec 2020 · delay flagged
SAL N. 103/2021 CANONE GENNAIO 2021
Issued 1 Feb 2021 · €94,219 · payment certified 1 Feb 2021 · delay flagged
SAL N. 104/2020 - 3° EXTRA CANONE A TUTTO IL 31.12.2020
Issued 19 Feb 2021 · €367,475 · payment certified 19 Feb 2021 · delay flagged
SAL N. 105/2021 - CANONE FEBBRAIO 2021
Issued 1 Mar 2021 · €94,219 · payment certified 1 Mar 2021 · delay flagged
SAL N. 106/2021 - CANONE MARZO 2021
Issued 1 Apr 2021 · €94,219 · payment certified 1 Apr 2021 · delay flagged
SAL N. 107/2021 - CANONE APRILE 2021
Issued 3 May 2021 · €94,219 · payment certified 3 May 2021 · delay flagged
SAL N. 108/2021 CANONE DAL 01 AL 20 MAGGIO 2021
Issued 24 May 2021 · €60,300 · payment certified 24 May 2021 · delay flagged
SAL 109/2021 DET. 283/2021 DAL 01 AL 20 MAGGIO 2021 - EXTRA CANONE FINALE
Issued 28 Jul 2021 · €478,559 · payment certified 28 Jul 2021 · delay flagged
RELAZIONE SUL CONTO FINALE E VERIFICA DI CONFORMITA' DEL SERVIZIO
Issued 21 Oct 2021 · €35,981 · payment certified 21 Oct 2021 · delay flagged
Loading comparison…
In sector Construction works in Lazio, 12.8% of comparable tenders drew at least 3 bidders (of 35283 tenders).
12.8% of comparable tenders had ≥3 bidders (n=35283)
Loading…
Loading…
Loading…
ANAC BDNCP — dati tabellari
Verify on ANACIngested: 5 Aug 2026
Release: 20260401-cig_csv.csv
Days to submit bids: 68