RESTAURO CONVENTO DEI GESUITI E CHIESA DI SAN FRANCESCO BORGIA
REGIONE SICILIANA
Amount
Award date
Bids
Published
Estimated tender value
Applicable legal ceiling
National maximum for this procedure type under D.Lgs 36/2023 — verify on official sources.
Award vs estimate
Sector
Loading actions…
Publication / start of procedure
8 Nov 2013
Step completedTime to submit bids
10 Jan 2014
63 days between opening and deadline
Step completedAward
1 Jul 2014
Step completedContract signed
29 Jun 2015
Step completedWork suspension
10 Jan 2022
Step completedWorks progress (SAL)
19 Sept 2016
Loading…
These are automated checks on public data. They help you decide what to look into — they are not criminal findings.
This contract triggered 6 pattern(s) worth a closer look:
Same supplier often · Works delayed (SAL)
- Repeated awards to the same supplier (same CA, 12 months) What does this mean?
- Works delayed (SAL) What does this mean?
- Long extension What does this mean?
- Final cost well above award
- No closure recorded
- Funding source not reported
| Supplier | Region | Amount | Award date | Status |
|---|---|---|---|---|
| L.S.V. COSTRUZIONI S.R.L. | — | €2,925,249 | 1 Jul 2014 | AGGIUDICATA |
| DI MARIA COSTRUZIONI S.R.L. | — | €2,925,249 | 1 Jul 2014 | AGGIUDICATA |
| EUROINFRASTRUTTURE S.R.L. | — | €2,925,249 | 1 Jul 2014 | AGGIUDICATA |
| Organisation | Role | Outcome |
|---|---|---|
| DI MARIA COSTRUZIONI S.R.L. 04488920879 | MANDATARIA | Awarded |
| EUROINFRASTRUTTURE S.R.L. 04022290870 | MANDANTE | Awarded |
| L.S.V. COSTRUZIONI S.R.L. 04777890874 | MANDANTE | Awarded |
Suspensions
CAUSE DI FORZA MAGGIORE
From 10 Jan 2022 · resumed on 11 Mar 2022
CAUSE DI FORZA MAGGIORE
From 10 Jan 2022 · resumed on 11 Mar 2022
REDAZIONE DI VARIANTI IN CORSO DI ESECUZIONE
From 17 Jan 2020 · resumed on 5 May 2020
REDAZIONE DI VARIANTI IN CORSO DI ESECUZIONE
From 17 Jan 2020 · resumed on 5 May 2020
STATO AVANZAMENTO N. 1 DEI LAVORI ESEGUITI A TUTTO IL 12/01/2016
Issued 21 Jan 2016 · €289,003 · payment certified 22 Jan 2016 · delay flagged
STATO AVANZAMENTO LAVORI N. 2 ESEGUITI A TUTTO IL 24/05/2016
Issued 30 May 2016 · €602,805 · payment certified 30 May 2016 · delay flagged
STATO AVANZAMENTO N. 3 DEI LAVORI ESEGUITI A TUTTO IL 18/07/2016
Issued 18 Jul 2016 · €906,950 · payment certified 18 Jul 2016 · delay flagged
STATO AVANZAMENTO N. 4 DEI LAVORI ESEGUITI A TUTTO IL 15/09/2016
Issued 19 Sept 2016 · €1,211,750 · payment certified 19 Sept 2016 · delay flagged
Loading comparison…
In sector Construction works in Sicily, 11.7% of comparable tenders drew at least 3 bidders (of 24468 tenders).
11.7% of comparable tenders had ≥3 bidders (n=24468)
Loading…
Loading…
Loading…
Source data & verification
ANAC BDNCP — dati tabellari
Verify on ANACIngested: 28 Jun 2026
Release: 20260601-cig_csv.csv
Days to submit bids: 63