COSTRUZIONE DI 22 ALLOGGI DI ERP

SOCIETA' PISTOIESE DI EDILIZIA SOCIALE S.P.A.

CIG 3917643D43Verify on ANACTuscany · Monsummano TermeWorksConstruction worksOpen procedureCode 45211340-4Risk signal — not an accusation of crime.
At a glance
Key figures from open ANAC records for this contract.

Amount

€1,750,483

Award date

5 Jun 2012

Bids

189

Published

15 Feb 2012

Estimated tender value

€2,227,270

Applicable legal ceiling

€150,000

National maximum for this procedure type under D.Lgs 36/2023 — verify on official sources.

Award vs estimate

-21.4%

Sector

Construction worksLAVORI DI COSTRUZIONE DI CONDOMINI
How do I verify this tender?

Loading actions…

Timeline
  1. Publication / start of procedure

    15 Feb 2012

    Step completed
  2. Time to submit bids

    12 Mar 2012

    26 days between opening and deadline

    Step completed
  3. Award

    5 Jun 2012

    Step completed
  4. Contract signed

    13 Sept 2012

    Step completed
  5. Contract variation

    18 Apr 2013

    Step completed
  6. Work suspension

    26 Oct 2012

    Step completed
  7. Works progress (SAL)

    20 Mar 2015

Delivery record

Loading…

In plain language

These are automated checks on public data. They help you decide what to look into — they are not criminal findings.

This contract triggered 6 pattern(s) worth a closer look:

Variation on record · Work suspended

Contracting authority (buyer)
Awarded to (suppliers)
1 award line(s) on record.
SupplierRegionAmountAward dateStatus
INDUSTRIA E SERVIZI S.R.L. IN LIQUIDAZIONE€1,750,4835 Jun 2012AGGIUDICATA
Who took part
1 participant(s) recorded on ANAC (not only the winner).
OrganisationRoleOutcome
INDUSTRIA E SERVIZI S.R.L. IN LIQUIDAZIONE

01148120999

Not reportedAwarded
What happened after the award
Variations and suspensions recorded on ANAC — read them with the signals, not as an accusation.

Variations

  • MIGLIORAMENTO O MIGLIORE FUNZIONALITA' DELLE PRESTAZIONI

    Approved on 18 Apr 2013 · 10

Suspensions

  • AVVERSE CONDIZIONI CLIMATICHE

    From 26 Oct 2012 · resumed on 1 Feb 2013

  • AVVERSE CONDIZIONI CLIMATICHE

    From 26 Oct 2012 · resumed on 1 Feb 2013

Works progress (SAL)
Progress certificates (stati di avanzamento) from ANAC — amounts and delays as published.
  • 1 SAL

    Issued 24 Apr 2013 · €286,707 · payment certified 11 Jun 2013 · delay flagged

  • 2 SAL

    Issued 10 Jun 2013 · €593,938 · payment certified 23 Jul 2013 · delay flagged

  • 3 SAL

    Issued 10 Sept 2013 · €842,911 · payment certified 7 Oct 2013 · delay flagged

  • 4 SAL

    Issued 18 Oct 2013 · €1,047,183 · payment certified 20 Nov 2013 · delay flagged

  • 5 SAL

    Issued 2 Apr 2014 · €1,220,419 · payment certified 2 Apr 2014 · delay flagged

  • 6 SAL

    Issued 29 Jul 2014 · €1,396,826 · payment certified 15 Sept 2014 · delay flagged

  • 7 SAL

    Issued 20 Mar 2015 · €1,563,769 · payment certified 9 Apr 2015 · delay flagged

Similar tenders in the same area

Loading comparison…

Market peer context
Market context from ANAC open data — not a full DIGIWHIST calibration.

In sector Construction works in Tuscany, 12.0% of comparable tenders drew at least 3 bidders (of 30271 tenders).

12% of comparable tenders had ≥3 bidders (n=30271)

UIF-aligned indicator (experimental)
Open-data risk indicator — for further review. Not a UIF/Bank of Italy endorsement.
Sector comparison

Loading…

Amount vs category

Loading…

Discount vs similar tenders

Loading…

Citizen verifier notes
Share what you verified on official sources — not a verdict
How the score is built
Ruleset 3.3.1 · 21 Sept 2026
Source data & verification

ANAC BDNCP — dati tabellari

Verify on ANAC

Ingested: 20 Sept 2026

Release: 20260801-cig_csv.csv

Days to submit bids: 26

COSTRUZIONE DI 22 ALLOGGI DI ERP — AppaltiWatch