LAVORI DI REALIZZAZIONE DI IMPIANTO DI ILLUMINAZIONE E ADEGUAMENTO BARRIERE DI SICUREZZA DELL'AUTOSTRADA TANGENZIALE OVEST DI MILANO
MILANO SERRAVALLE - MILANO TANGENZIALI S.P.A.
Amount
Award date
Bids
Published
Estimated tender value
Applicable legal ceiling
National maximum for this procedure type under D.Lgs 36/2023 — verify on official sources.
Award vs estimate
Sector
Loading actions…
Publication / start of procedure
22 Nov 2010
Step completedTime to submit bids
18 Jan 2011
57 days between opening and deadline
Step completedAward
21 Mar 2013
Step completedContract signed
30 Jan 2014
Step completedContract variation
11 Mar 2021
Step completedWork suspension
1 Mar 2021
Step completedWorks progress (SAL)
3 Jun 2021
Loading…
These are automated checks on public data. They help you decide what to look into — they are not criminal findings.
This contract triggered 7 pattern(s) worth a closer look:
Same supplier often · Only one offer admitted
- Repeated awards to the same supplier (same CA, 12 months) What does this mean?
- Only one offer admitted What does this mean?
- Discount very different from similar tenders What does this mean?
- Works delayed (SAL) What does this mean?
- Long extension What does this mean?
- No start recorded
- Funding source not reported
Lombardy · More tenders in this area
AUSA code: 0000168085
ASSAGO
Authority profile| Supplier | Region | Amount | Award date | Status |
|---|---|---|---|---|
| CAR SEGNALETICA STRADALE SRL | — | €38,814,710 | 21 Mar 2013 | AGGIUDICATA |
| Organisation | Role | Outcome |
|---|---|---|
| CAR SEGNALETICA STRADALE SRL 01049090622 | Not reported | Awarded |
Variations
ART.132 C.1 LETT. B) D.LGS.163/2006
Approved on 11 Mar 2021 · 2
ART.132 C.3 II CV D.LGS.163/2006
Approved on 10 May 2018 · 6
ART.132 C.3 II CV D.LGS.163/2006
Approved on 3 Dec 2014 · 6
Suspensions
CAUSE DI FORZA MAGGIORE
From 1 Mar 2021 · resumed on 29 Mar 2021
CAUSE DI FORZA MAGGIORE
From 1 Mar 2021 · resumed on 29 Mar 2021
CAUSE DI FORZA MAGGIORE
From 1 Mar 2021 · resumed on 29 Mar 2021
PUBBLICO INTERESSE O NECESSITA'
From 16 Mar 2020 · resumed on 14 Apr 2020
PUBBLICO INTERESSE O NECESSITA'
From 16 Mar 2020 · resumed on 14 Apr 2020
PUBBLICO INTERESSE O NECESSITA'
From 16 Mar 2020 · resumed on 14 Apr 2020
PUBBLICO INTERESSE O NECESSITA'
From 22 May 2015 · resumed on 3 Nov 2015
PUBBLICO INTERESSE O NECESSITA'
From 22 May 2015 · resumed on 3 Nov 2015
PUBBLICO INTERESSE O NECESSITA'
From 22 May 2015 · resumed on 3 Nov 2015
Progress step 1
Issued 30 Jan 2014 · €628,194 · payment certified 14 Feb 2014 · delay flagged
Progress step 2
Issued 9 Apr 2014 · €2,728,969 · payment certified 11 Apr 2014 · delay flagged
Progress step 3
Issued 11 Jun 2014 · €4,617,122 · payment certified 13 Jun 2014 · delay flagged
Progress step 4
Issued 25 Jul 2014 · €7,028,983 · payment certified 4 Aug 2014 · delay flagged
Progress step 5
Issued 24 Sept 2014 · €10,137,676 · payment certified 15 Oct 2014 · delay flagged
Progress step 6
Issued 20 Nov 2014 · €14,145,289 · payment certified 15 Dec 2014 · delay flagged
Progress step 7
Issued 5 Feb 2015 · €15,713,409 · payment certified 13 Feb 2015 · delay flagged
Progress step 8
Issued 14 Apr 2015 · €18,614,009 · payment certified 14 Apr 2015 · delay flagged
Progress step 9
Issued 11 Jun 2015 · €19,850,164 · payment certified 12 Jun 2015 · delay flagged
Progress step 10
Issued 31 Jul 2015 · €20,065,585 · payment certified 17 Aug 2015 · delay flagged
Progress step 11
Issued 17 Feb 2016 · €20,339,552 · payment certified 17 Feb 2016 · delay flagged
Progress step 12
Issued 1 Apr 2016 · €20,588,818 · payment certified 14 Apr 2016 · delay flagged
Progress step 13
Issued 21 Nov 2016 · €20,913,155 · payment certified 15 Dec 2016 · delay flagged
Progress step 14
Issued 13 Jul 2017 · €21,680,638 · payment certified 13 Jul 2017 · delay flagged
Progress step 15
Issued 26 Jul 2018 · €22,151,751 · payment certified 27 Jul 2018 · delay flagged
Progress step 16
Issued 16 Apr 2019 · €22,889,851 · payment certified 6 May 2019 · delay flagged
Progress step 17
Issued 23 Jul 2019 · €23,491,059 · payment certified 29 Jul 2019 · delay flagged
Progress step 18
Issued 10 Oct 2019 · €24,261,315 · payment certified 14 Oct 2019 · delay flagged
Progress step 19
Issued 28 Nov 2019 · €25,162,892 · payment certified 6 Dec 2019 · delay flagged
Progress step 20
Issued 23 Jan 2020 · €26,266,366 · payment certified 3 Feb 2020 · delay flagged
Progress step 21
Issued 9 Apr 2020 · €27,467,205 · payment certified 14 Apr 2020 · delay flagged
Progress step 22
Issued 3 Jun 2020 · €28,467,382 · payment certified 15 Jun 2020 · delay flagged
Progress step 23
Issued 29 Jul 2020 · €29,920,766 · payment certified 30 Jul 2020 · delay flagged
STATO D'AVANZAMENTO LAVORI
Issued 22 Dec 2020 · €31,171,713 · payment certified 22 Dec 2020 · delay flagged
SAL N. 1 - COSTI DELLA SICUREZZA PER PROCEDURE ANTI CONTAGIO DA CORONA VIRUS COVID-19 AI SENSI DELL?ART. 8, COMMA 4 LETTERA B) DEL DECRETO LEGGE N°76/2020 DEL 16 LUGLIO
Issued 31 Dec 2020 · €119,680 · payment certified 19 Mar 2021 · delay flagged
SAL 2 COSTI COVID
Issued 3 Jun 2021 · €143,348 · payment certified 3 Jun 2021 · delay flagged
STATO AVANZAMENTO LAVORI
Issued 19 Mar 2021 · €32,541,925 · payment certified 19 Mar 2021 · delay flagged
STATO AVANZAMENTO LAVORI
Issued 3 Jun 2021 · €34,703,865 · payment certified 3 Jun 2021 · delay flagged
Loading comparison…
In sector Construction works in Lombardy, 10.7% of comparable tenders drew at least 3 bidders (of 49549 tenders).
10.7% of comparable tenders had ≥3 bidders (n=49549)
Loading…
Loading…
Loading…
Source data & verification
ANAC BDNCP — dati tabellari
Verify on ANACIngested: 6 Jul 2026
Release: 20260501-cig_csv.csv
Days to submit bids: 57