LAVORI DI COMPLETAMENTO DEL RECUPERO DELL'EX CONVITTO PALMIERI DI LECCE
PROVINCIA DI LECCE
Amount
Award date
Bids
Published
Estimated tender value
Applicable legal ceiling
National maximum for this procedure type under D.Lgs 36/2023 — verify on official sources.
Award vs estimate
Sector
Loading actions…
Publication / start of procedure
13 Aug 2010
Step completedTime to submit bids
15 Oct 2010
63 days between opening and deadline
Step completedAward
17 Dec 2010
Step completedContract signed
29 May 2012
Step completedContract variation
13 Feb 2015
Step completedWork suspension
23 May 2014
Step completedWorks progress (SAL)
14 Jan 2015
Loading…
These are automated checks on public data. They help you decide what to look into — they are not criminal findings.
This contract triggered 7 pattern(s) worth a closer look:
Variation on record · Multiple variations
- Contract variation recorded on ANAC What does this mean?
- Multiple variations on the same contract What does this mean?
- Work suspension recorded What does this mean?
- Works delayed (SAL) What does this mean?
- Long extension What does this mean?
- Final cost well above award
- No closure recorded
| Supplier | Region | Amount | Award date | Status |
|---|---|---|---|---|
| TROSO OSVALDO S.R.L. | — | €1,589,175 | 17 Dec 2010 | AGGIUDICATA |
| Organisation | Role | Outcome |
|---|---|---|
| TROSO OSVALDO S.R.L. 04304460753 | Not reported | Awarded |
Variations
ART. 205 C.2 D.LGS 163/2006
Approved on 13 Feb 2015 · 99
ART.132 C.3 II CV D.LGS.163/2006
Approved on 3 Apr 2014 · 6
Suspensions
PUBBLICO INTERESSE O NECESSITA'
From 23 May 2014 · resumed on 26 May 2014
PUBBLICO INTERESSE O NECESSITA'
From 23 May 2014 · resumed on 26 May 2014
STATO DI AVANZAMENTO N°1 A TUTTO IL 18/02/2013
Issued 18 Feb 2013 · €164,933 · payment certified 8 Mar 2013 · delay flagged
STATO DI AVANZAMENTO N°2 A TUTTO IL 13/062013
Issued 13 Jun 2013 · €384,186 · payment certified 14 Jun 2013 · delay flagged
STATO DI AVANZAMENTO N°3 A TUTTO IL 24/10/2013
Issued 24 Oct 2013 · €482,191 · payment certified 24 Oct 2013 · delay flagged
STATO DI AVANZAMENTO N°4 A TUTTO IL 05/12/2013- IMPORTO SAL ?. 620.244,01 DI CUI ?.615.244,01 PER LAVORI ED ?.5.000,00 PER ONERI SULLA SICUREZZA NON SOGGETTI A RIBASSO.
Issued 5 Dec 2013 · €620,244 · payment certified 5 Dec 2013 · delay flagged
STATO DI AVANZAMENTO N.5 A TUTTO IL 07/02/2014 (IMPORTO SAL EURO 736.791,07 DI CUI EURO 731.791,07 COMPONENTE LAVORI ED EURO 5.000,00 PER ONERI PER LA SICUREZZA)
Issued 7 Feb 2014 · €736,791 · payment certified 10 Feb 2014 · delay flagged
STATO AVANZAMENTO LAVORI N.6 A TUTTO IL 12/04/2014 (IMPORTO SAL PARI AD EURO 848.745,42 DI CUI EURO 842.745,42 PER COMPONENTE LAVORI ED EURO 6.000,00 PER ONERI PER LA SICUREZZA)
Issued 12 Apr 2014 · €848,745 · payment certified 29 Apr 2014 · delay flagged
STATO AVANZAMENTO LAVORI N.7 A TUTTO IL 26/05/2014 (IMPORTO SAL PARI AD EURO 1.124.577,61 DI CUI EURO 1.094.427,61 PER COMPONENTE LAVORI ED EURO 30.150,00 PER ONERI PER LA SICUREZZA)
Issued 26 May 2014 · €1,124,578 · payment certified 26 May 2014 · delay flagged
STATO AVANZAMENTO LAVORI N.8 A TUTTO IL 25/07/2014 (IMPORTO SAL PARI AD EURO 1.377.588,54 DI CUI EURO 1.345.438,54 PER COMPONENTE LAVORI ED EURO 32.150,00 PER ONERI PER LA SICUREZZA)
Issued 25 Jul 2014 · €1,377,589 · payment certified 25 Jul 2014 · delay flagged
STATO AVANZAMENTO LAVORI N.9 A TUTTO IL 14/01/2015 (IMPORTO SAL PARI AD EURO 1.554.301,93 DI CUI EURO 1.521.151,93 PER COMPONENTE LAVORI ED EURO 33.150,00 PER ONERI PER LA SICUREZZA)
Issued 14 Jan 2015 · €1,554,302 · payment certified 15 Jan 2015 · delay flagged
Loading comparison…
In sector Construction works, 11.5% of comparable tenders drew at least 3 bidders (of 414197 tenders).
11.5% of comparable tenders had ≥3 bidders (n=414197)
Loading…
Loading…
Loading…
Source data & verification
ANAC BDNCP — dati tabellari
Verify on ANACIngested: 20 Sept 2026
Release: 20260801-cig_csv.csv
Days to submit bids: 63