APPROFONDIMENTO E RISANAMENTO DEL CANALE PIOMBONE

AUTORITA' DI SISTEMA PORTUALE DEL MARE ADRIATICO CENTRO-SETTENTRIONALE

CIG 0494988D01Verify on ANACEmilia-RomagnaWorksConstruction worksOpen procedureCode 45252124-3Risk signal — not an accusation of crime.
At a glance
Key figures from open ANAC records for this contract.

Amount

€45,162,864

Award date

28 Jan 2011

Bids

4

Published

18 Jun 2010

Estimated tender value

€29,915,972

Applicable legal ceiling

€150,000

National maximum for this procedure type under D.Lgs 36/2023 — verify on official sources.

Award vs estimate

+51.0%

Sector

Construction worksLAVORI DI DRAGAGGIO E DI POMPAGGIO
How do I verify this tender?

Loading actions…

Timeline
  1. Publication / start of procedure

    18 Jun 2010

    Step completed
  2. Time to submit bids

    19 Aug 2010

    62 days between opening and deadline

    Step completed
  3. Award

    28 Jan 2011

    Step completed
  4. Contract signed

    26 Jul 2012

    Step completed
  5. Contract variation

    7 Oct 2024

    Step completed
  6. Work suspension

    11 Apr 2025

    Step completed
  7. Works progress (SAL)

    28 May 2026

Delivery record

Loading…

In plain language

These are automated checks on public data. They help you decide what to look into — they are not criminal findings.

This contract triggered 6 pattern(s) worth a closer look:

Discount very different from similar tenders · Works delayed (SAL)

Contracting authority (buyer)
Awarded to (suppliers)
2 award line(s) on record.
SupplierRegionAmountAward dateStatus
NAUTILUS S.R.L.€22,581,43228 Jan 2011AGGIUDICATA
C.G.X. COSTRUZIONI GENERALI XODO S.R.L.€22,581,43228 Jan 2011AGGIUDICATA
Who took part
2 participant(s) recorded on ANAC (not only the winner).
OrganisationRoleOutcome
C.G.X. COSTRUZIONI GENERALI XODO S.R.L.

00569180292

MANDANTEAwarded
NAUTILUS S.R.L.

02924640275

MANDATARIAAwarded
What happened after the award
Variations and suspensions recorded on ANAC — read them with the signals, not as an accusation.

Variations

  • DP 373 APPROVAZIONE SOMMA EOGATADAL MIT DD 80/2024 02.04.2024- APPROVATA LA SOMMA RICHIESTA 8CONTABILIZZAZIONE ANNO 2023) CON ACCESSO AL FONDO DEL 31.01.24, DI CUI ALL''ART 26 DEL DL 50/2022 SMI , PARI A? 102.629,49.

    Approved on 7 Oct 2024 · 99

  • INTERVENTO DI BY-PASS DELLE ACQUE CONSORZIALI NELL?AREA DI RINATURALIZZAZIONE

    Approved on 4 Sept 2024 · 99

  • SISTEMAZIONE AREA ?EX PORTO CARNI? E MODIFICHE TECNICO/STRUTTURALI AL PROGETTO FINALIZZATE AL MIGLIORAMENTO DELL''OPERA ED ALLA SUA FUNZIONALITÀ (CONFERIMENTO DELLE ACQUE CONSORTILI ALL?INTERNO DELL?AREA DI RINATURALIZZAZIONE)

    Approved on 29 Dec 2023 · 99

  • EVENTI IMPREVISTI E IMPREVEDIBILI DURANTE LA SOSPENSIONE E MODIFICHE TECNICO/STRUTTURALI FINALIZZATE AL MIGLIORAMENTO DELL''OPERA ED ALLA SUA FUNZIONALITÀ

    Approved on 21 Dec 2022 · 99

  • ART. 132 C. 3 I CV, D.LGS. 163/2006

    Approved on 10 Jun 2016 · 99

Suspensions

  • AVVERSE CONDIZIONI CLIMATICHE

    From 11 Apr 2025 · resumed on 19 May 2025

  • AVVERSE CONDIZIONI CLIMATICHE

    From 11 Apr 2025 · resumed on 19 May 2025

  • AVVERSE CONDIZIONI CLIMATICHE

    From 11 Apr 2025 · resumed on 19 May 2025

  • AVVERSE CONDIZIONI CLIMATICHE

    From 11 Apr 2025 · resumed on 19 May 2025

  • AVVERSE CONDIZIONI CLIMATICHE

    From 11 Apr 2025 · resumed on 19 May 2025

  • AVVERSE CONDIZIONI CLIMATICHE

    From 11 Apr 2025 · resumed on 19 May 2025

  • AVVERSE CONDIZIONI CLIMATICHE

    From 27 Feb 2025 · resumed on 1 Apr 2025

  • AVVERSE CONDIZIONI CLIMATICHE

    From 27 Feb 2025 · resumed on 1 Apr 2025

  • AVVERSE CONDIZIONI CLIMATICHE

    From 27 Feb 2025 · resumed on 1 Apr 2025

  • AVVERSE CONDIZIONI CLIMATICHE

    From 27 Feb 2025 · resumed on 1 Apr 2025

  • AVVERSE CONDIZIONI CLIMATICHE

    From 27 Feb 2025 · resumed on 1 Apr 2025

  • AVVERSE CONDIZIONI CLIMATICHE

    From 27 Feb 2025 · resumed on 1 Apr 2025

  • AVVERSE CONDIZIONI CLIMATICHE

    From 28 Nov 2024 · resumed on 17 Feb 2025

  • AVVERSE CONDIZIONI CLIMATICHE

    From 28 Nov 2024 · resumed on 17 Feb 2025

  • AVVERSE CONDIZIONI CLIMATICHE

    From 28 Nov 2024 · resumed on 17 Feb 2025

  • AVVERSE CONDIZIONI CLIMATICHE

    From 28 Nov 2024 · resumed on 17 Feb 2025

  • AVVERSE CONDIZIONI CLIMATICHE

    From 28 Nov 2024 · resumed on 17 Feb 2025

  • AVVERSE CONDIZIONI CLIMATICHE

    From 28 Nov 2024 · resumed on 17 Feb 2025

  • AVVERSE CONDIZIONI CLIMATICHE

    From 16 Sept 2024 · resumed on 27 Nov 2024

  • AVVERSE CONDIZIONI CLIMATICHE

    From 16 Sept 2024 · resumed on 27 Nov 2024

  • AVVERSE CONDIZIONI CLIMATICHE

    From 16 Sept 2024 · resumed on 27 Nov 2024

  • AVVERSE CONDIZIONI CLIMATICHE

    From 16 Sept 2024 · resumed on 27 Nov 2024

  • AVVERSE CONDIZIONI CLIMATICHE

    From 16 Sept 2024 · resumed on 27 Nov 2024

  • AVVERSE CONDIZIONI CLIMATICHE

    From 16 Sept 2024 · resumed on 27 Nov 2024

  • INTERFERENZE DI NATURA TECNICA

    From 12 Jun 2023 · resumed on 21 Aug 2023

  • INTERFERENZE DI NATURA TECNICA

    From 12 Jun 2023 · resumed on 21 Aug 2023

  • INTERFERENZE DI NATURA TECNICA

    From 12 Jun 2023 · resumed on 21 Aug 2023

  • INTERFERENZE DI NATURA TECNICA

    From 12 Jun 2023 · resumed on 21 Aug 2023

  • INTERFERENZE DI NATURA TECNICA

    From 12 Jun 2023 · resumed on 21 Aug 2023

  • INTERFERENZE DI NATURA TECNICA

    From 12 Jun 2023 · resumed on 21 Aug 2023

  • INTERVENTO AUTORITA' GIUDIZIARIA

    From 19 Dec 2019 · resumed on 11 Jan 2023

  • INTERVENTO AUTORITA' GIUDIZIARIA

    From 19 Dec 2019 · resumed on 11 Jan 2023

  • INTERVENTO AUTORITA' GIUDIZIARIA

    From 19 Dec 2019 · resumed on 11 Jan 2023

  • INTERVENTO AUTORITA' GIUDIZIARIA

    From 19 Dec 2019 · resumed on 11 Jan 2023

  • INTERVENTO AUTORITA' GIUDIZIARIA

    From 19 Dec 2019 · resumed on 11 Jan 2023

  • INTERVENTO AUTORITA' GIUDIZIARIA

    From 19 Dec 2019 · resumed on 11 Jan 2023

  • INTERFERENZE DI NATURA TECNICA

    From 19 Dec 2018 · resumed on 21 May 2019

  • INTERFERENZE DI NATURA TECNICA

    From 19 Dec 2018 · resumed on 21 May 2019

  • INTERFERENZE DI NATURA TECNICA

    From 19 Dec 2018 · resumed on 21 May 2019

  • INTERFERENZE DI NATURA TECNICA

    From 19 Dec 2018 · resumed on 21 May 2019

  • INTERFERENZE DI NATURA TECNICA

    From 19 Dec 2018 · resumed on 21 May 2019

  • INTERFERENZE DI NATURA TECNICA

    From 19 Dec 2018 · resumed on 21 May 2019

  • INTERFERENZE DI NATURA TECNICA

    From 5 Feb 2016 · resumed on 24 Nov 2016

  • INTERFERENZE DI NATURA TECNICA

    From 5 Feb 2016 · resumed on 24 Nov 2016

  • INTERFERENZE DI NATURA TECNICA

    From 5 Feb 2016 · resumed on 24 Nov 2016

  • INTERFERENZE DI NATURA TECNICA

    From 5 Feb 2016 · resumed on 24 Nov 2016

  • INTERFERENZE DI NATURA TECNICA

    From 5 Feb 2016 · resumed on 24 Nov 2016

  • INTERFERENZE DI NATURA TECNICA

    From 5 Feb 2016 · resumed on 24 Nov 2016

  • INTERFERENZE DI NATURA TECNICA

    From 2 Jul 2015 · resumed on 17 Sept 2015

  • INTERFERENZE DI NATURA TECNICA

    From 2 Jul 2015 · resumed on 17 Sept 2015

  • INTERFERENZE DI NATURA TECNICA

    From 2 Jul 2015 · resumed on 17 Sept 2015

  • INTERFERENZE DI NATURA TECNICA

    From 2 Jul 2015 · resumed on 17 Sept 2015

  • INTERFERENZE DI NATURA TECNICA

    From 2 Jul 2015 · resumed on 17 Sept 2015

  • INTERFERENZE DI NATURA TECNICA

    From 2 Jul 2015 · resumed on 17 Sept 2015

  • INTERFERENZE DI NATURA TECNICA

    From 3 Jun 2015 · resumed on 29 Jun 2015

  • INTERFERENZE DI NATURA TECNICA

    From 3 Jun 2015 · resumed on 29 Jun 2015

  • INTERFERENZE DI NATURA TECNICA

    From 3 Jun 2015 · resumed on 29 Jun 2015

  • INTERFERENZE DI NATURA TECNICA

    From 3 Jun 2015 · resumed on 29 Jun 2015

  • INTERFERENZE DI NATURA TECNICA

    From 3 Jun 2015 · resumed on 29 Jun 2015

  • INTERFERENZE DI NATURA TECNICA

    From 3 Jun 2015 · resumed on 29 Jun 2015

  • PUBBLICO INTERESSE O NECESSITA'

    From 15 May 2014 · resumed on 3 Jun 2015

  • PUBBLICO INTERESSE O NECESSITA'

    From 15 May 2014 · resumed on 3 Jun 2015

  • PUBBLICO INTERESSE O NECESSITA'

    From 15 May 2014 · resumed on 3 Jun 2015

  • PUBBLICO INTERESSE O NECESSITA'

    From 15 May 2014 · resumed on 3 Jun 2015

  • PUBBLICO INTERESSE O NECESSITA'

    From 15 May 2014 · resumed on 3 Jun 2015

  • PUBBLICO INTERESSE O NECESSITA'

    From 15 May 2014 · resumed on 3 Jun 2015

Works progress (SAL)
Progress certificates (stati di avanzamento) from ANAC — amounts and delays as published.
  • Progress step 1

    Issued 26 Jul 2012 · €3,866,638 · payment certified 28 Sept 2012 · delay flagged

  • Progress step 2

    Issued 24 Dec 2012 · €5,420,755 · payment certified 14 Jan 2013 · delay flagged

  • Progress step 3

    Issued 1 Feb 2013 · €7,174,982 · payment certified 25 Feb 2013 · delay flagged

  • Progress step 4

    Issued 16 May 2013 · €8,438,662 · payment certified 6 Jun 2013 · delay flagged

  • Progress step 5

    Issued 5 Jul 2013 · €9,612,084 · payment certified 7 Aug 2013 · delay flagged

  • Progress step 6

    Issued 8 Aug 2013 · €10,679,044 · payment certified 12 Sept 2013 · delay flagged

  • Progress step 7

    Issued 7 Oct 2013 · €11,750,891 · payment certified 6 Nov 2013 · delay flagged

  • Progress step 8

    Issued 10 Mar 2014 · €12,808,758 · payment certified 4 Apr 2014 · delay flagged

  • Progress step 9

    Issued 1 Oct 2014 · €14,075,025 · payment certified 27 Oct 2014 · delay flagged

  • Progress step 10

    Issued 3 Jun 2015 · €14,582,625 · payment certified 10 Jun 2015 · delay flagged

  • Progress step 11

    Issued 9 Mar 2016 · €15,003,891 · payment certified 15 Mar 2016 · delay flagged

  • Progress step 12

    Issued 26 Oct 2016 · €15,522,690 · payment certified 3 Nov 2016 · delay flagged

  • Progress step 13

    Issued 28 Jun 2017 · €16,282,135 · payment certified 17 Jul 2017 · delay flagged

  • Progress step 14

    Issued 8 Aug 2017 · €17,341,922 · payment certified 23 Aug 2017 · delay flagged

  • Progress step 15

    Issued 18 Oct 2017 · €18,357,096 · payment certified 16 Nov 2017 · delay flagged

  • Progress step 16

    Issued 27 Nov 2017 · €19,035,622 · payment certified 22 Dec 2017 · delay flagged

  • Progress step 17

    Issued 15 Feb 2018 · €19,795,983 · payment certified 1 Mar 2018 · delay flagged

  • Progress step 18

    Issued 20 Mar 2018 · €20,491,028 · payment certified 10 Apr 2018 · delay flagged

  • Progress step 19

    Issued 16 Apr 2018 · €21,158,426 · payment certified 2 May 2018 · delay flagged

  • Progress step 20

    Issued 23 May 2018 · €21,927,631 · payment certified 7 Aug 2018 · delay flagged

  • Progress step 21

    Issued 3 Oct 2018 · €22,484,317 · payment certified 26 Nov 2018 · delay flagged

  • SAL N. 22

    Issued 28 Jun 2019 · €23,239,902 · payment certified 29 Jul 2019 · delay flagged

  • ?FALLIMENTO PIACENTINI COSTRUZIONI S.P.A. N. 123/2019 ? SENTENZA N. 126/2019 DEL TRIBUNALE DI MODENA?

    Issued 30 Apr 2021 · €23,759,975 · payment certified 1 Jun 2021 · delay flagged

  • S.A.L. N. 24 - CORRISPOSTA ANTICIPAZIONEDEL 20% SU IMPORTO VARIANTE N.3 PARI A ? 873.921,82 CON CDP DEL 21/12/2022.

    Issued 8 May 2023 · €24,747,882 · payment certified 25 May 2023 · delay flagged

  • SAL 25

    Issued 17 Oct 2023 · €25,579,057 · payment certified 30 Oct 2023 · delay flagged

  • Progress step 26

    Issued 15 Feb 2024 · €26,290,177 · payment certified 18 Mar 2024 · delay flagged

  • SAL 27

    Issued 11 Sept 2024 · €26,960,917 · payment certified 19 Sept 2024 · delay flagged

  • SAL 28

    Issued 11 Apr 2025 · €27,494,393 · payment certified 18 Apr 2025 · delay flagged

  • SAL 29 TRASMESSO DAL D.L. PEC PROT. ADSP 1009 DEL 22.01.2026

    Issued 22 Jan 2026 · €28,674,877 · payment certified 30 Jan 2026 · delay flagged

  • SAL N. 30

    Issued 28 May 2026 · €29,453,727 · payment certified 12 Jun 2026 · delay flagged

Similar tenders in the same area

Loading comparison…

Market peer context
Market context from ANAC open data — not a full DIGIWHIST calibration.

In sector Construction works in Emilia-Romagna, 9.0% of comparable tenders drew at least 3 bidders (of 29516 tenders).

9% of comparable tenders had ≥3 bidders (n=29516)

UIF-aligned indicator (experimental)
Open-data risk indicator — for further review. Not a UIF/Bank of Italy endorsement.
Sector comparison

Loading…

Amount vs category

Loading…

Discount vs similar tenders

Loading…

Citizen verifier notes
Share what you verified on official sources — not a verdict
How the score is built
Ruleset 3.3.1 · 21 Sept 2026
Source data & verification

ANAC BDNCP — dati tabellari

Verify on ANAC

Ingested: 20 Sept 2026

Release: 20260801-cig_csv.csv

Days to submit bids: 62