PA12/09 - AFFIDAMENTO A CONTRAENTE GENERALE DELLA REALIZZAZIONE CON QUALSIASI MESSO DELL'OPERA ITINERARIO AGRIGENTO-CALTANISSETA-A19. SS 640 DI PORTO EMPEDOCLE. AMMODERNAMENTO E ADEGUAMENTO ALLA CAT. B DEL D.M. 5/11/2001. TRATTO 2: DAL KM. 44+000 ALLO SVINCOLO CON LA A19.

ANAS - SOCIETA' PER AZIONI

CIG 03446004E9Verify on ANACLazioWorksConstruction worksRestricted procedureCode 45233120-6Risk signal — not an accusation of crime.
At a glance
Key figures from open ANAC records for this contract.

Amount

€1,703,302,337

Award date

13 Apr 2010

Bids

8

Published

13 Jul 2009

Estimated tender value

€787,552,957

Applicable legal ceiling

€150,000

National maximum for this procedure type under D.Lgs 36/2023 — verify on official sources.

Award vs estimate

-27.9%

Sector

Construction worksLAVORI DI COSTRUZIONE DI STRADE
How do I verify this tender?

Loading actions…

Timeline
  1. Publication / start of procedure

    13 Jul 2009

    Step completed
  2. Time to submit bids

    13 Oct 2009

    92 days between opening and deadline

    Step completed
  3. Award

    13 Apr 2010

    Step completed
  4. Contract signed

    30 Jun 2010

    Step completed
  5. Contract variation

    22 Feb 2017

    Step completed
  6. Works progress (SAL)

    19 Nov 2025

Delivery record

Loading…

In plain language

These are automated checks on public data. They help you decide what to look into — they are not criminal findings.

This contract triggered 8 pattern(s) worth a closer look:

Same supplier often · Variation on record

Contracting authority (buyer)
Awarded to (suppliers)
3 award line(s) on record.
SupplierRegionAmountAward dateStatus
TECNIS S.P.A.—€567,767,44613 Apr 2010AGGIUDICATA
EMPEDOCLE 2 SOCIETA' CONSORTILE PER AZIONI—€567,767,44613 Apr 2010AGGIUDICATA
COOPERATIVA MURATORI & CEMENTISTI C.M.C. DI RAVENNA SOCIETA' COOPERATIVA—€567,767,44613 Apr 2010AGGIUDICATA
Who took part
3 participant(s) recorded on ANAC (not only the winner).
OrganisationRoleOutcome
COOPERATIVA MURATORI & CEMENTISTI C.M.C. DI RAVENNA SOCIETA' COOPERATIVA

00084280395

Not reportedAwarded
EMPEDOCLE 2 SOCIETA' CONSORTILE PER AZIONI

02379310390

Not reportedAwarded
TECNIS S.P.A.

02766640870

Not reportedAwarded
What happened after the award
Variations and suspensions recorded on ANAC — read them with the signals, not as an accusation.

Variations

  • ART. 176 COMM. 5 LETT. B) DEL D.LGS 163/2006 E DELL''ART. 162 COMM. 1 DEL DPR 207/10 E DELL''ART 11 DEL C.S.A

    Approved on 22 Feb 2017 · 99

  • ART. 176 COMM. 5 LETT. B) DEL D.LGS 163/2006 E DELL''ART. 162 COMM. 1 DEL DPR 207/10

    Approved on 29 Sept 2016 · 99

  • ART.132 C.3 II CV D.LGS.163/2006

    Approved on 2 Dec 2013 · 6

Works progress (SAL)
Progress certificates (stati di avanzamento) from ANAC — amounts and delays as published.
  • Progress step 1

    Issued 22 Mar 2012 · €6,995,000 · payment certified 4 Apr 2012 · delay flagged

  • Progress step 2

    Issued 11 Sept 2013 · €27,408,755 · payment certified 13 Sept 2013 · delay flagged

  • Progress step 3

    Issued 10 Dec 2013 · €57,960,477 · payment certified 12 Dec 2013 · delay flagged

  • Progress step 4

    Issued 20 Dec 2013 · €85,061,918 · payment certified 7 Feb 2014 · delay flagged

  • Progress step 5

    Issued 17 Jul 2014 · €109,368,333 · payment certified 22 Jul 2014 · delay flagged

  • Progress step 6

    Issued 7 Oct 2014 · €144,278,675 · payment certified 22 Oct 2014 · delay flagged

  • Progress step 7

    Issued 19 Dec 2014 · €177,753,152 · payment certified 23 Dec 2014 · delay flagged

  • LAVORI A TUTTO IL 13/03/2015

    Issued 2 Apr 2015 · €201,523,822 · payment certified 7 Apr 2015 · delay flagged

  • Progress step 9

    Issued 31 Jul 2015 · €228,889,229 · payment certified 31 Jul 2015 · delay flagged

  • Progress step 10

    Issued 29 Sept 2015 · €250,226,798 · payment certified 30 Sept 2015 · delay flagged

  • Progress step 11

    Issued 21 Dec 2015 · €279,611,824 · payment certified 12 Jan 2016 · delay flagged

  • LAVORI A TUTTO IL 22/03/2016

    Issued 23 Mar 2016 · €308,477,020 · payment certified 23 Mar 2016 · delay flagged

  • LAVORI A TUTTO IL 16/05/16

    Issued 23 May 2016 · €331,109,487 · payment certified 24 May 2016 · delay flagged

  • LAVORI A TUTTO IL 29/06/2016

    Issued 7 Jul 2016 · €357,700,644 · payment certified 13 Jul 2016 · delay flagged

  • LAVORI A TUTTO IL 15/09/16

    Issued 20 Sept 2016 · €402,627,984 · payment certified 20 Sept 2016 · delay flagged

  • LAVORI A TUTTO IL 08/11/2016

    Issued 9 Nov 2016 · €424,630,919 · payment certified 14 Nov 2016 · delay flagged

  • SAL A TUTTO IL 20/12/2016

    Issued 21 Dec 2016 · €455,544,322 · payment certified 22 Dec 2016 · delay flagged

  • SAL A TUTTO IL 11/04/2017

    Issued 13 Apr 2017 · €497,578,502 · payment certified 13 Apr 2017 · delay flagged

  • Progress step 19

    Issued 3 Aug 2017 · €524,479,137 · payment certified 3 Aug 2017 · delay flagged

  • Progress step 20

    Issued 28 Sept 2017 · €563,374,471 · payment certified 28 Sept 2017 · delay flagged

  • SAL A TUTTO IL 07/11/2017

    Issued 20 Nov 2017 · €584,347,992 · payment certified 22 Nov 2017 · delay flagged

  • LAVORI A TUTTO IL 19/03/2018

    Issued 20 Mar 2018 · €612,246,422 · payment certified 22 Mar 2018 · delay flagged

  • SAL A TUTTO IL 28/05/2018

    Issued 7 Jun 2018 · €629,004,620 · payment certified 7 Jun 2018 · delay flagged

  • LAVORI A TUTTO IL 28/05/2018

    Issued 7 Jun 2018 · €629,004,620 · payment certified 7 Jun 2018 · delay flagged

  • LAVORI A TUTTO IL 10/10/2018

    Issued 12 Oct 2018 · €646,988,145 · payment certified 16 Oct 2018 · delay flagged

  • LAVORI A TUTTO IL 28/02/2019

    Issued 7 Mar 2019 · €653,812,527 · payment certified 11 Mar 2019 · delay flagged

  • SAL A TUTTO IL 28/08/2019

    Issued 29 Oct 2019 · €655,555,045 · payment certified 29 Oct 2019 · delay flagged

  • SAL A TUTTO IL 12/12/2019

    Issued 15 Dec 2019 · €656,337,763 · payment certified 20 Dec 2019 · delay flagged

  • SAL A TUTTO IL 06/03/2020

    Issued 2 Apr 2020 · €656,907,083 · payment certified 2 Apr 2020 · delay flagged

  • SAL A TUTTO IL 05/08/2020

    Issued 2 Sept 2020 · €657,812,200 · payment certified 3 Sept 2020 · delay flagged

  • SAL A TUTTO IL 25/11/2020

    Issued 16 Dec 2020 · €659,504,316 · payment certified 17 Dec 2020 · delay flagged

  • A TUTTO IL 09/03/2021

    Issued 1 Apr 2021 · €662,967,648 · payment certified 6 Apr 2021 · delay flagged

  • A TUTTO IL 10/05/2021

    Issued 25 Jun 2021 · €665,723,806 · payment certified 28 Jun 2021 · delay flagged

  • A TUTTO IL 23/07/2021

    Issued 3 Aug 2021 · €668,451,986 · payment certified 5 Aug 2021 · delay flagged

  • A TUTTO IL 05/10/2021

    Issued 29 Oct 2021 · €672,085,701 · payment certified 2 Nov 2021 · delay flagged

  • A TUTTO IL 15/11/2021

    Issued 3 Dec 2021 · €674,464,419 · payment certified 9 Dec 2021 · delay flagged

  • A TUTTO IL 15/12/2021

    Issued 16 Dec 2021 · €675,962,491 · payment certified 17 Dec 2021 · delay flagged

  • SAL A TUTTO IL 02/03/2022

    Issued 9 Mar 2022 · €682,001,302 · payment certified 10 Mar 2022 · delay flagged

  • SAL A TUTTO IL 28/03/2022

    Issued 6 Apr 2022 · €683,809,405 · payment certified 8 Apr 2022 · delay flagged

  • SAL A TUTTO IL 20/05/2022

    Issued 27 May 2022 · €685,789,308 · payment certified 1 Jun 2022 · delay flagged

  • SAL A TUTTO IL 08/07/2022

    Issued 20 Jul 2022 · €687,498,417 · payment certified 25 Jul 2022 · delay flagged

  • STATO D'AVANZAMENTO LAVORI

    Issued 10 Aug 2022 · €689,023,669 · payment certified 11 Aug 2022 · delay flagged

  • A TUTTO IL 09/09/2022

    Issued 20 Sept 2022 · €690,919,768 · payment certified 22 Sept 2022 · delay flagged

  • A TOTTO IL 11/10/2022

    Issued 25 Oct 2022 · €693,247,698 · payment certified 24 Oct 2022 · delay flagged

  • SAL A TUTOO IL 11/11/2022

    Issued 23 Nov 2022 · €695,377,749 · payment certified 25 Nov 2022 · delay flagged

  • A TUTTO IL 16/12/2022

    Issued 10 Jan 2023 · €697,194,302 · payment certified 13 Jan 2023 · delay flagged

  • A TUTTO IL 24/02/2023

    Issued 2 Mar 2023 · €698,815,950 · payment certified 7 Mar 2023 · delay flagged

  • SAL A TUTTO IL 03/04/2023

    Issued 19 Apr 2023 · €700,379,688 · payment certified 21 Apr 2023 · delay flagged

  • SAL A TUTTO IL 08/06/2023

    Issued 27 Jun 2023 · €706,834,683 · payment certified 3 Jul 2023 · delay flagged

  • SAL A TUTTO IL 08/07/2023

    Issued 26 Jul 2023 · €710,851,155 · payment certified 31 Jul 2023 · delay flagged

  • SAL A TUTTO IL \\T08/09/2023

    Issued 17 Oct 2023 · €712,833,246 · payment certified 23 Oct 2023 · delay flagged

  • SAL A TUTTO IL 13/10/2023

    Issued 15 Nov 2023 · €714,833,944 · payment certified 17 Nov 2023 · delay flagged

  • SAL A TUTTO IL 21/11/2023

    Issued 5 Dec 2023 · €717,037,663 · payment certified 11 Dec 2023 · delay flagged

  • SAL A TUTTO IL 21/12/2023

    Issued 21 Dec 2023 · €719,476,933 · payment certified 22 Dec 2023 · delay flagged

  • SAL A TUTTO IL 31/01/2024

    Issued 12 Feb 2024 · €725,315,277 · payment certified 13 Feb 2024 · delay flagged

  • SAL A TUTTO IL 01/03/2024

    Issued 12 Mar 2024 · €728,581,311 · payment certified 13 Mar 2024 · delay flagged

  • SAL A TUTTO IL 02/04/2024

    Issued 17 Apr 2024 · €733,852,047 · payment certified 18 Apr 2024 · delay flagged

  • SAL A TUTTO IL \\T02/05/2024

    Issued 21 May 2024 · €738,169,068 · payment certified 27 May 2024 · delay flagged

  • SAL A TUTTO IL 03/06/2024

    Issued 18 Jun 2024 · €740,828,375 · payment certified 24 Jun 2024 · delay flagged

  • SAL A TUTTO IL 03/07/2024

    Issued 17 Jul 2024 · €742,995,146 · payment certified 19 Jul 2024 · delay flagged

  • SAL A TUTTO IL \\T03/08/2024

    Issued 2 Sept 2024 · €745,951,829 · payment certified 3 Sept 2024 · delay flagged

  • SAL A TUTTO IL 10/09/2024

    Issued 24 Sept 2024 · €751,668,256 · payment certified 26 Sept 2024 · delay flagged

  • 10/10/2024

    Issued 23 Oct 2024 · €755,296,397 · payment certified 24 Oct 2024 · delay flagged

  • SAL A TUTTO IL 11/11/2024

    Issued 27 Nov 2024 · €762,432,509 · payment certified 29 Nov 2024 · delay flagged

  • SAL A TUTTO 11/12/2024

    Issued 27 Dec 2024 · €765,838,826 · payment certified 2 Jan 2025 · delay flagged

  • SAL A TUTTO 11/01/2025

    Issued 28 Jan 2025 · €768,253,363 · payment certified 28 Jan 2025 · delay flagged

  • SAL A TUTTO IL 11/02/2025

    Issued 25 Feb 2025 · €772,501,942 · payment certified 28 Feb 2025 · delay flagged

  • SAL A TUTTO IL \\T11/03/2025

    Issued 24 Mar 2025 · €776,785,338 · payment certified 26 Mar 2025 · delay flagged

  • SAL A TUTTO 11/04/2025

    Issued 24 Apr 2025 · €779,969,810 · payment certified 28 Apr 2025 · delay flagged

  • SAL A TUTTO 12/05/2025

    Issued 26 May 2025 · €782,519,122 · payment certified 29 May 2025 · delay flagged

  • SAL A TUTTO \\T12/06/2025

    Issued 30 Jun 2025 · €786,001,025 · payment certified 7 Jul 2025 · delay flagged

  • SAL A TUTTO \\T12/07/2025

    Issued 31 Jul 2025 · €789,012,188 · payment certified 4 Aug 2025 · delay flagged

  • SAL A TUTTO IL 22/08/2025

    Issued 16 Sept 2025 · €792,584,158 · payment certified 18 Sept 2025 · delay flagged

  • SAL A TUTTO 26/09/2025

    Issued 22 Oct 2025 · €795,893,858 · payment certified 5 Dec 2025 · delay flagged

  • SAL A TUTTO 27/10/2025

    Issued 19 Nov 2025 · €798,915,773 · payment certified 15 Dec 2025 · delay flagged

Similar tenders in the same area

Loading comparison…

Market peer context
Market context from ANAC open data — not a full DIGIWHIST calibration.

In sector Construction works in Lazio, 12.8% of comparable tenders drew at least 3 bidders (of 35283 tenders).

12.8% of comparable tenders had ≥3 bidders (n=35283)

UIF-aligned indicator (experimental)
Open-data risk indicator — for further review. Not a UIF/Bank of Italy endorsement.
Sector comparison

Loading…

Amount vs category

Loading…

Discount vs similar tenders

Loading…

Citizen verifier notes
Share what you verified on official sources — not a verdict
How the score is built
Ruleset 3.3.1 · 27 Sept 2026
Source data & verification

ANAC BDNCP — dati tabellari

Verify on ANAC

Ingested: 20 Sept 2026

Release: 20260801-cig_csv.csv

Days to submit bids: 92