RIQUALIFICAZIONE PARCO DI SAN BOVIO
COMUNE DI PESCHIERA BORROMEO
Amount
Award date
Bids
Published
Estimated tender value
Applicable legal ceiling
National maximum for this procedure type under D.Lgs 36/2023 — verify on official sources.
Award vs estimate
Sector
Loading actions…
Publication / start of procedure
26 Jun 2008
Step completedTime to submit bids
22 Jul 2008
26 days between opening and deadline
Step completedAward
11 Aug 2008
Step completedContract signed
4 Dec 2008
Step completedContract variation
27 Apr 2009
Step completedWork suspension
18 Dec 2008
Step completedWorks progress (SAL)
31 Mar 2009
Loading…
These are automated checks on public data. They help you decide what to look into — they are not criminal findings.
This contract triggered 8 pattern(s) worth a closer look:
Variation on record · Multiple variations
- Contract variation recorded on ANAC What does this mean?
- Multiple variations on the same contract What does this mean?
- Work suspension recorded What does this mean?
- Discount very different from similar tenders What does this mean?
- Works delayed (SAL) What does this mean?
- Long extension What does this mean?
- No start recorded
- Funding source not reported
Lombardy · More tenders in this area
AUSA code: 0000247521
PESCHIERA BORROMEO
Authority profile| Supplier | Region | Amount | Award date | Status |
|---|---|---|---|---|
| FLOEMA S.R.L. | — | €192,074 | 11 Aug 2008 | AGGIUDICATA |
| Organisation | Role | Outcome |
|---|---|---|
| FLOEMA S.R.L. 02198630416 | Not reported | Awarded |
Variations
ART.132 C.1 LETT. C) D.LGS.163/2006
Approved on 27 Apr 2009 · 3
ART.132 C.1 LETT. A) D.LGS. 163/2006
Approved on 29 Dec 2008 · 99
Suspensions
AVVERSE CONDIZIONI CLIMATICHE
From 18 Dec 2008 · resumed on 9 Feb 2009
AVVERSE CONDIZIONI CLIMATICHE
From 18 Dec 2008 · resumed on 9 Feb 2009
Progress step 1
Issued 4 Dec 2008 · €115,474 · payment certified 4 Dec 2008 · delay flagged
Progress step 2
Issued 16 Feb 2009 · €78,130 · payment certified 16 Feb 2009 · delay flagged
Progress step 3
Issued 31 Mar 2009 · €37,247 · payment certified 2 Apr 2009 · delay flagged
Loading comparison…
In sector Construction works in Lombardy, 11.3% of comparable tenders drew at least 3 bidders (of 51978 tenders).
11.3% of comparable tenders had ≥3 bidders (n=51978)
Loading…
Loading…
Loading…
Source data & verification
ANAC BDNCP — dati tabellari
Verify on ANACIngested: 5 Aug 2026
Release: 20260401-cig_csv.csv
Days to submit bids: 26