AFFIDAMENTO A CONTRAENTE GENERALE DELLA PROGETTAZIONE DEFINITIVA ED ESECUTIVA E REALIZZAZIONE CON QUALSIASI MEZZO DEL 1° LOTTO DELLE TANGENZIALI DI COMO E DI VARESE E DELLA TRATTA A8 - A9 DEL COLLEGAMENTO AUTOSTRADALE DALMINE-COMO-VARESE-VALICO DEL GAGGIOLO E OPERE CONNESSE.
AUTOSTRADA PEDEMONTANA LOMBARDA S.P.A.
Amount
Award date
Bids
Published
Estimated tender value
Applicable legal ceiling
National maximum for this procedure type under D.Lgs 36/2023 — verify on official sources.
Award vs estimate
Sector
Loading actions…
Publication / start of procedure
27 Jul 2007
Step completedTime to submit bids
27 Feb 2008
215 days between opening and deadline
Step completedAward
13 Jun 2008
Step completedContract signed
26 Feb 2010
Step completedContract variation
11 Dec 2014
Step completedWorks progress (SAL)
26 Jan 2021
Loading…
These are automated checks on public data. They help you decide what to look into — they are not criminal findings.
This contract triggered 7 pattern(s) worth a closer look:
Very long deadlines · Variation on record
- Unusually long bid submission period (>90 days) — opposite DIGIWHIST literature tail
- Contract variation recorded on ANAC What does this mean?
- Multiple variations on the same contract What does this mean?
- Discount very different from similar tenders What does this mean?
- Works delayed (SAL) What does this mean?
- Final cost well above award
- Significant subcontracting
Lombardy · More tenders in this area
AUSA code: 0000232048
MILANO
Authority profile| Supplier | Region | Amount | Award date | Status |
|---|---|---|---|---|
| PEDELOMBARDA SOCIETA' CONSORTILE PER AZIONI | — | €629,664,724 | 13 Jun 2008 | AGGIUDICATA |
| Organisation | Role | Outcome |
|---|---|---|
| PEDELOMBARDA SOCIETA' CONSORTILE PER AZIONI 06294710964 | Not reported | Awarded |
Variations
ART. 176 D. LGS. 163/2006
Approved on 11 Dec 2014 · 99
ART. 176 DEL D. LGS. 163/2006
Approved on 6 Mar 2014 · 99
ART. 176 DEL D.LGS. 163/2006
Approved on 31 Oct 2012 · 99
ART.132 C.1 LETT. A) D.LGS.163/2006
Approved on 30 Jun 2011 · 1
1) CAUSE IMPREVISTE E IMPREVEDIBILI (ART. 132 C.1 LETT. B D.LGS. 163/2006); 2) OTTEMPERANZA PRESCRIZIONI CIPE; 3) DETERMINAZIONI COLLEGIO DI VIGILANZA DELL''ACCORDO DI PROGRAMMA
Approved on 4 Feb 2010 · 99
Progress step 1
Issued 26 Feb 2010 · €18,269,484 · payment certified 22 Mar 2010 · delay flagged
Progress step 2
Issued 30 Apr 2010 · €18,651,235 · payment certified 10 Jun 2010 · delay flagged
Progress step 3
Issued 31 May 2010 · €19,051,015 · payment certified 24 Jun 2010 · delay flagged
Progress step 4
Issued 30 Jun 2010 · €19,323,670 · payment certified 30 Jul 2010 · delay flagged
Progress step 5
Issued 31 Jul 2010 · €20,177,031 · payment certified 6 Aug 2010 · delay flagged
Progress step 6
Issued 31 Aug 2010 · €20,658,490 · payment certified 27 Sept 2010 · delay flagged
Progress step 7
Issued 30 Sept 2010 · €21,754,599 · payment certified 4 Nov 2010 · delay flagged
Progress step 8
Issued 31 Oct 2010 · €22,162,893 · payment certified 9 Dec 2010 · delay flagged
Progress step 9
Issued 30 Nov 2010 · €34,302,135 · payment certified 3 Jan 2011 · delay flagged
Progress step 10
Issued 31 Dec 2010 · €35,610,203 · payment certified 4 Feb 2011 · delay flagged
Progress step 11
Issued 31 Jan 2011 · €39,629,592 · payment certified 15 Mar 2011 · delay flagged
Progress step 12
Issued 28 Feb 2011 · €48,642,363 · payment certified 26 Apr 2011 · delay flagged
Progress step 13
Issued 31 Mar 2011 · €52,565,825 · payment certified 31 May 2011 · delay flagged
Progress step 14
Issued 30 Apr 2011 · €58,130,992 · payment certified 28 Jun 2011 · delay flagged
Progress step 15
Issued 31 May 2011 · €62,718,980 · payment certified 30 Jul 2011 · delay flagged
Progress step 16
Issued 30 Jun 2011 · €65,745,812 · payment certified 4 Aug 2011 · delay flagged
Progress step 17
Issued 31 Jul 2011 · €73,677,158 · payment certified 30 Aug 2011 · delay flagged
Progress step 18
Issued 31 Aug 2011 · €80,292,282 · payment certified 30 Sept 2011 · delay flagged
Progress step 19
Issued 30 Sept 2011 · €88,721,021 · payment certified 31 Oct 2011 · delay flagged
Progress step 20
Issued 31 Oct 2011 · €99,730,213 · payment certified 30 Nov 2011 · delay flagged
Progress step 21
Issued 30 Nov 2011 · €113,033,835 · payment certified 30 Dec 2011 · delay flagged
Progress step 22
Issued 31 Dec 2011 · €125,078,884 · payment certified 10 Feb 2012 · delay flagged
Progress step 23
Issued 31 Jan 2012 · €137,178,125 · payment certified 13 Mar 2012 · delay flagged
Progress step 24
Issued 29 Feb 2012 · €149,501,032 · payment certified 6 Apr 2012 · delay flagged
Progress step 25
Issued 31 Mar 2012 · €169,428,474 · payment certified 11 May 2012 · delay flagged
Progress step 26
Issued 30 Apr 2012 · €185,522,456 · payment certified 8 Jun 2012 · delay flagged
Progress step 27
Issued 31 May 2012 · €208,933,885 · payment certified 8 Jul 2012 · delay flagged
Progress step 28
Issued 30 Jun 2012 · €238,094,158 · payment certified 9 Aug 2012 · delay flagged
Progress step 29
Issued 31 Jul 2012 · €264,482,994 · payment certified 31 Oct 2012 · delay flagged
Progress step 30
Issued 31 Aug 2012 · €285,516,614 · payment certified 6 Nov 2012 · delay flagged
Progress step 31
Issued 30 Sept 2012 · €316,719,488 · payment certified 22 Nov 2012 · delay flagged
Progress step 32
Issued 31 Oct 2012 · €346,561,781 · payment certified 10 Dec 2012 · delay flagged
Progress step 33
Issued 30 Nov 2012 · €374,276,714 · payment certified 7 Jan 2013 · delay flagged
Progress step 34
Issued 31 Dec 2012 · €394,455,651 · payment certified 6 Feb 2013 · delay flagged
Progress step 35
Issued 31 Jan 2013 · €422,090,679 · payment certified 7 Mar 2013 · delay flagged
Progress step 36
Issued 28 Feb 2013 · €445,946,890 · delay flagged
Progress step 37
Issued 31 Mar 2013 · €470,256,935 · payment certified 8 May 2013 · delay flagged
Progress step 38
Issued 30 Apr 2013 · €491,871,580 · payment certified 6 Jun 2013 · delay flagged
Progress step 39
Issued 31 May 2013 · €518,104,733 · payment certified 8 Jul 2013 · delay flagged
Progress step 40
Issued 30 Jun 2013 · €546,940,124 · payment certified 8 Aug 2013 · delay flagged
Progress step 41
Issued 31 Jul 2013 · €582,131,149 · payment certified 10 Sept 2013 · delay flagged
Progress step 42
Issued 31 Aug 2013 · €612,274,401 · payment certified 9 Oct 2013 · delay flagged
Progress step 43
Issued 30 Sept 2013 · €647,829,913 · payment certified 8 Nov 2013 · delay flagged
Progress step 44
Issued 30 Oct 2013 · €686,630,657 · payment certified 12 Dec 2013 · delay flagged
Progress step 45
Issued 30 Nov 2013 · €724,481,612 · payment certified 10 Jan 2014 · delay flagged
Progress step 46
Issued 31 Dec 2013 · €748,062,757 · payment certified 14 Feb 2014 · delay flagged
Progress step 47
Issued 31 Jan 2014 · €758,813,236 · payment certified 14 Mar 2014 · delay flagged
Progress step 48
Issued 6 Mar 2014 · €758,813,236 · payment certified 25 Mar 2014 · delay flagged
Progress step 49
Issued 31 Mar 2014 · €788,846,900 · payment certified 30 May 2014 · delay flagged
Progress step 50
Issued 30 Apr 2014 · €805,563,943 · payment certified 18 Jun 2014 · delay flagged
Progress step 51
Issued 31 May 2014 · €821,144,803 · payment certified 18 Jul 2014 · delay flagged
Progress step 52
Issued 30 Jun 2014 · €844,057,526 · payment certified 27 Aug 2014 · delay flagged
Progress step 53
Issued 31 Jul 2014 · €857,009,811 · payment certified 26 Sept 2014 · delay flagged
Progress step 54
Issued 31 Aug 2014 · €863,668,486 · payment certified 15 Oct 2014 · delay flagged
Progress step 55
Issued 30 Sept 2014 · €877,752,444 · payment certified 21 Nov 2014 · delay flagged
Progress step 56
Issued 31 Oct 2014 · €889,698,102 · payment certified 22 Dec 2014 · delay flagged
Progress step 57
Issued 30 Nov 2014 · €894,129,415 · payment certified 29 Jan 2015 · delay flagged
Progress step 58
Issued 31 Dec 2014 · €901,884,598 · payment certified 6 Mar 2015 · delay flagged
Progress step 59
Issued 31 Jan 2015 · €907,277,007 · payment certified 26 Mar 2015 · delay flagged
Progress step 60
Issued 20 Feb 2015 · €910,151,572 · payment certified 29 Apr 2015 · delay flagged
Progress step 61
Issued 31 Mar 2015 · €912,502,683 · payment certified 22 May 2015 · delay flagged
Progress step 62
Issued 30 Apr 2015 · €919,525,432 · payment certified 29 May 2015 · delay flagged
Progress step 63
Issued 11 May 2015 · €925,882,099 · payment certified 29 May 2015 · delay flagged
Progress step 64
Issued 31 Mar 2014 · €772,329,698 · payment certified 15 Apr 2014 · delay flagged
Progress step 65
Issued 25 Jan 2016 · €1,187,688 · payment certified 28 Jan 2016 · delay flagged
Progress step 66
Issued 16 Dec 2016 · €927,805,875 · payment certified 16 Dec 2016 · delay flagged
Progress step 67
Issued 10 Oct 2015 · €925,881,689 · payment certified 17 Dec 2015 · delay flagged
Progress step 68
Issued 26 Jul 2018 · €927,805,465 · payment certified 26 Jul 2018 · delay flagged
Progress step 69
Issued 26 Jan 2021 · €623,500 · payment certified 26 Jan 2021 · delay flagged
Loading comparison…
In sector Construction works in Lombardy, 11.3% of comparable tenders drew at least 3 bidders (of 51978 tenders).
11.3% of comparable tenders had ≥3 bidders (n=51978)
Loading…
Loading…
Loading…
Source data & verification
ANAC BDNCP — dati tabellari
Verify on ANACIngested: 25 Jul 2026
Release: 20260701-cig_csv.csv
Days to submit bids: 215